6552 N ENCINO AVE 91406
Certificate Information: 6552 N ENCINO AVE 91406
- Application / Permit
- 20010-20000-02243
- Plan Check / Job No.
- B20VN08771
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DET (46'X28'6") 1-STORY ACCESSORY DWELLING UNIT PER ORD #186,481.
- Permit Issued
- Issued on 5/10/2021
- Issuing Office
- Current Status
- CofO Issued on 9/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 7/14/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/10/2021 | HAYATO TSUCHIYA |
| Issued | 5/10/2021 | APPLICANT |
| Building Plans Picked Up | 5/13/2021 | APPLICANT |
| CofO in Progress | 9/16/2022 | SEAN HAUPT |
| CofO Issued | 9/21/2022 | MICHAEL SMITH |
| Permit Finaled | 9/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/4/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 12/17/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/17/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 12/18/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2020 | GABRIEL ROBLES |
| ZI | Cleared | 2/10/2021 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 2/17/2021 | JEREMY CARTER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hagopyan,, Edmond; Lic. No.: C80143 | 7939 WENTWORTH STREET SUNLAND, CA 91040 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/4/2021 | Partial Inspection | STEVEN BACK |
| HVAC-Rough | 10/15/2021 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 10/15/2021 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 10/21/2021 | Approved | SEAN HAUPT |
| Sewer | 10/27/2021 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 11/8/2021 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/25/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 2/25/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 2/25/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 2/25/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 2/25/2022 | Approved | SEAN HAUPT |
| Verify Sprinkler Sign Off | 2/25/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/10/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 3/10/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/22/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 4/5/2022 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Not Ready | SEAN HAUPT |
| Underground Mechanical | 4/5/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 4/15/2022 | Corrections Issued | SEAN HAUPT |
| Final | 4/15/2022 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 4/15/2022 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 4/15/2022 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Final | 9/2/2022 | Approved | SEAN HAUPT |
| Final | 9/2/2022 | Partial Approval | SEAN HAUPT |
| Green Building Final | 9/2/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 9/2/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 9/2/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 9/2/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 9/2/2022 | Approved | SEAN HAUPT |
| Smoke Detectors | 9/2/2022 | Approved | SEAN HAUPT |