2254 1/2 N GLOVER PL 90031
Certificate Information: 2254 1/2 N GLOVER PL 90031
- Application / Permit
- 20010-20000-02219
- Plan Check / Job No.
- B20VN08741
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 21'-0" X 23'-0" ONE STORY ACCESSORY DWELLING UNIT per GCS 65852.2(e)(1)(B)
- Permit Issued
- Issued on 11/24/2020
- Issuing Office
- Current Status
- CofO Issued on 9/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 7/10/2020 | ARTIN ZARUKIAN |
| Issued | 11/24/2020 | APPLICANT |
| CofO in Progress | 8/4/2022 | THOMAS LOGRASSO |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| Permit Finaled | 9/16/2022 | DEROLD HAUFF |
| CofO Issued | 9/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 8/13/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/13/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Construction near power lines | Cleared | 10/30/2020 | RIDWAN HARDY |
| ZI | Cleared | 11/4/2020 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/26/2021 | Partial Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 6/4/2021 | Partial Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 6/10/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/23/2021 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 7/6/2021 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 8/23/2021 | Corrections Issued | THOMAS LOGRASSO |
| Sewer | 8/23/2021 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 8/23/2021 | Partial Approval | THOMAS LOGRASSO |
| Gas Test | 8/26/2021 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/26/2021 | Approved | THOMAS LOGRASSO |
| Sewer | 8/26/2021 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 8/26/2021 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 10/13/2021 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 1/28/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 1/28/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 2/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 2/11/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Rough | 2/11/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Rough | 2/11/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 2/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/4/2022 | Conditional Approval | THOMAS LOGRASSO |
| HVAC-Rough | 3/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 3/4/2022 | Conditional Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/21/2022 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 3/21/2022 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 3/21/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 3/21/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Drywall Nailing | 4/6/2022 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/6/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 4/6/2022 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 4/14/2022 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 5/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Service/Power Release | 5/9/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 6/10/2022 | Partial Inspection | THOMAS LOGRASSO |
| Green Building Final | 6/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| MERV13>=Final | 6/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Service/Power Release | 6/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 6/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 6/15/2022 | Corrections Issued | THOMAS LOGRASSO |
| Final | 6/23/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 6/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 6/23/2022 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/23/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 6/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 6/23/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 6/30/2022 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 6/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Service/Power Release | 6/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Smoke Detectors | 6/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/3/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 8/3/2022 | Approved | THOMAS LOGRASSO |
| Service/Power Release | 8/3/2022 | Approved | THOMAS LOGRASSO |
| Smoke Detectors | 8/3/2022 | Approved | THOMAS LOGRASSO |