11353 W ALLEGHENY ST 91352

Certificate Information: 11353 W ALLEGHENY ST 91352

Application / Permit
20010-20000-02210
Plan Check / Job No.
B20VN08679
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT ( 39'-0"X27'-3") PER LAMC 12.22 A.33(c)¹, (d)¹, and (g) FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 1/24/2022
Issuing Office
Current Status
CofO Issued on 9/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 MOHAMMAD ESMAILI
Corrections Issued 7/30/2020 MOHAMMAD ESMAILI
Quality Review Completed 8/17/2020 OMID HEDAYAT
Building Plans Picked Up 8/19/2020 APPLICANT
Applicant returned to address corrections 11/5/2021 MOHAMMAD ESMAILI
Plan Check Approved 12/15/2021 MOHAMMAD ESMAILI
Issued 1/24/2022 APPLICANT
CofO in Progress 7/10/2023 DAVID ANDERSON
CofO Issued 9/18/2023 RUBEN SALAS
Permit Finaled 9/18/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/26/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/28/2020 ADRIAN CASTRO
Specific Plan Cleared 9/23/2020 PEGGY MALONE-BROWN
ZI Cleared 9/23/2020 PEGGY MALONE-BROWN
Grading Pre-Inspection Cleared 2/5/2021 BRIAN MILLER
Private sewage disp. approval Cleared 7/19/2021 DAN RYAN EVANGELISTA
Hydrant and Access approval Cleared 7/23/2021 MATTHEW CRAIG
Low Impact Development Cleared 9/30/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/4/2021 GABRIEL ROBLES
GPI Written Notices Cleared 11/5/2021 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/21/2022 Corrections Issued CHRISTOPHER DELLEFIELD
METHANE-Barrier 4/21/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
METHANE-Subgrade 4/21/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/25/2022 Approved CHRISTOPHER DELLEFIELD
METHANE-Barrier 4/25/2022 Approved CHRISTOPHER DELLEFIELD
METHANE-Subgrade 4/25/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 4/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 5/19/2022 Approved MATTHEW NELSON
PLUMBING-Rough 5/19/2022 Approved MATTHEW NELSON
ELECTRICAL-Rough 8/18/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Approved DAVID ANDERSON
Green Building Rough 8/18/2022 Approved DAVID ANDERSON
HVAC-Rough 8/18/2022 Approved DAVID ANDERSON
METHANE-Rough 8/18/2022 Approved DAVID ANDERSON
PLUMBING-Rough 8/18/2022 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 8/18/2022 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/29/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 9/14/2022 Approved DAVID ANDERSON
Insulation 9/14/2022 Approved DAVID ANDERSON
Drywall Nailing 9/21/2022 Approved DAVID ANDERSON
Underground Mechanical 1/23/2023 Approved DAVID ANDERSON
Final 6/20/2023 Corrections Issued DAVID ANDERSON
Green Building Final 6/20/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 6/20/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 6/20/2023 Not Ready for Inspection DAVID ANDERSON
Smoke Detectors 6/20/2023 Approved DAVID ANDERSON
Final 7/7/2023 OK to Issue CofO DAVID ANDERSON
Service/Power Release 7/7/2023 Approved DAVID ANDERSON