2285 W MOSS AVE 90065
Certificate Information: 2285 W MOSS AVE 90065
- Application / Permit
- 20010-20000-02201
- Plan Check / Job No.
- B20VN08665
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 11'-8" X 19'-10" DETACHED GARAGE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/3/2020
- Issuing Office
- Current Status
- CofO Issued on 5/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2020 | RAPHAEL ROSAS |
| Corrections Issued | 7/3/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/21/2020 | ROSENDO MEDINA |
| Plan Check Approved | 9/11/2020 | ROSENDO MEDINA |
| Issued | 10/3/2020 | APPLICANT |
| CofO in Progress | 5/17/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 5/20/2021 | DEROLD HAUFF |
| CofO Issued | 5/20/2021 | DEROLD HAUFF |
| Permit Finaled | 5/20/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/24/2020 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 7/31/2020 | ROSA SILVA |
| Specific Plan | Cleared | 8/3/2020 | NASHYA JENSEN |
| ZI | Cleared | 8/3/2020 | NASHYA JENSEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2020 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hajdari,, Gentjan; Lic. No.: C88031 | 157 S LOS ROBLES AVE 12 PASADENA, CA 91101 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/1/2020 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 12/9/2020 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/15/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 1/15/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/24/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Final | 2/24/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/24/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 5/17/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 5/17/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |