430 E 92ND ST 90003

Certificate Information: 430 E 92ND ST 90003

Application / Permit
20010-20000-02194
Plan Check / Job No.
B20VN08630
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'X 32'-8" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
CofO Issued on 4/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2020 APPLICANT
Assigned to Plan Check Engineer 8/18/2020 SELLA BENYAMIN
Corrections Issued 8/20/2020 SELLA BENYAMIN
Plan Check Approved 11/2/2020 SELLA BENYAMIN
Issued 12/1/2020 APPLICANT
Building Plans Picked Up 12/8/2020 APPLICANT
CofO in Progress 4/7/2021 EUGENE CASSIDY
Permit Finaled 4/14/2021 DEROLD HAUFF
CofO Issued 4/14/2021 DEROLD HAUFF
Permit Finaled 4/14/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/27/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/27/2020 CELINA MORENO
Low Impact Development Cleared 10/2/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/9/2020 ELAINE LEI
Hydrant and Access approval Cleared 10/13/2020 MATTHEW CRAIG
Sewer availability Cleared 10/27/2020 ELAINE LEI

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/7/2020 Conditional Approval EUGENE CASSIDY
Footing/Foundation/Slab 12/11/2020 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 12/15/2020 Not Ready for Inspection OSVALDO PARAMO
Grounding or Bonding 12/15/2020 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 12/24/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 12/24/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 1/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 1/12/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
HVAC-Rough 1/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/12/2021 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 1/12/2021 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 1/12/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/15/2021 Approved EUGENE CASSIDY
HVAC-Rough 1/15/2021 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 1/15/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 1/15/2021 Approved EUGENE CASSIDY
Wood Frame 1/15/2021 Approved EUGENE CASSIDY
Insulation 1/19/2021 Approved OSVALDO PARAMO
Drywall Nailing 1/25/2021 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/25/2021 Approved JOHN KLARIN
ELECTRICAL-Final 3/25/2021 Approved JOHN KLARIN
Final 3/25/2021 Corrections Issued JOHN KLARIN
Green Building Final 3/25/2021 Corrections Issued JOHN KLARIN
Green Building Rough 3/25/2021 Approved JOHN KLARIN
HVAC-Final 3/25/2021 Approved JOHN KLARIN
PLUMBING-Final 3/25/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved JOHN KLARIN
Service/Power Release 3/25/2021 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 3/25/2021 Approved JOHN KLARIN
Verify Sprinkler Sign Off 3/25/2021 Approved JOHN KLARIN
Service/Power Release 4/5/2021 Corrections Issued EUGENE CASSIDY
Final 4/7/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 4/7/2021 Approved EUGENE CASSIDY
Service/Power Release 4/7/2021 Approved EUGENE CASSIDY