2874 1/2 W AVENUE 35 90065

Certificate Information: 2874 1/2 W AVENUE 35 90065

Application / Permit
20010-20000-02190
Plan Check / Job No.
B20VN08611
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 39'1" X 28'10" 1ST FLOOR STORAGE ROOM WITH ATTACHED TWO CAR GARAGE AND WITH 2ND FLOOR ACCESSORY DWELLING UNIT ABOVE AS PER LAMC 12.22.A.33(C) AND (D), ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/18/2022
Issuing Office
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 RARES BODEA
Corrections Issued 7/25/2020 RARES BODEA
Quality Review Completed 7/31/2020 STEVEN KIM
Building Plans Picked Up 8/4/2020 APPLICANT
Applicant returned to address corrections 11/22/2021 RARES BODEA
Applicant returned to address corrections 2/1/2022 RARES BODEA
Plan Check Approved 3/2/2022 RARES BODEA
Issued 3/18/2022 APPLICANT
CofO in Progress 2/13/2025 THOMAS LOGRASSO
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/4/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/5/2021 CECILIO NAVARRO
Sewer availability Cleared 5/5/2021 CECILIO NAVARRO
Supp. Use District POD/CDO/TDO Cleared 5/27/2021 ADRINEH MELKONIAN
ZI Cleared 5/27/2021 ADRINEH MELKONIAN
Hydrant and Access approval Cleared 6/9/2021 JOHN CONNEALLY
Low Impact Development Cleared 10/21/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/22/2021 CECILIO NAVARRO
GPI Written Notices Cleared 11/22/2021 RARES BODEA
Grading Pre-Inspection Cleared 11/22/2021 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/24/2022 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/24/2022 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 10/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/4/2022 Approved HAMIK HARTOUNIAN
Underground Mechanical 11/9/2022 No Access for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 3/23/2023 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/27/2023 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Partial Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 7/27/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 8/7/2023 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 8/8/2023 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/11/2023 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 9/14/2023 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 9/14/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/14/2023 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Rough 9/14/2023 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 9/14/2023 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/19/2023 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/19/2023 Approved HAMIK HARTOUNIAN
Insulation 11/1/2023 Partial Approval HAMIK HARTOUNIAN
Insulation 11/7/2023 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/7/2023 Approved HAMIK HARTOUNIAN
Sewer 1/30/2024 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/1/2024 Approved HAMIK HARTOUNIAN
Grounding or Bonding 3/1/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 3/12/2024 Approved BRIAN SULLIVAN
Final 8/2/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 8/13/2024 No Access for Inspection THOMAS LOGRASSO
Final 8/16/2024 Corrections Issued THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Not Required THOMAS LOGRASSO
Smoke Detectors 8/16/2024 Approved THOMAS LOGRASSO
Final 2/7/2025 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 2/7/2025 Approved THOMAS LOGRASSO
MERV13>=Final 2/7/2025 Approved THOMAS LOGRASSO
Service/Power Release 2/7/2025 Not Required THOMAS LOGRASSO
Deputy Wood Construction 2/13/2025 Conditional Approval THOMAS LOGRASSO
Final 2/13/2025 OK to Issue CofO THOMAS LOGRASSO