10363 N FERNGLEN AVE 91042
Certificate Information: 10363 N FERNGLEN AVE 91042
- Application / Permit
- 20010-20000-02187
- Plan Check / Job No.
- B20VN08607
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 7/2/2021
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/26/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 8/13/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 8/19/2020 | APPLICANT |
| Applicant returned to address corrections | 2/26/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/18/2021 | MOHAMMAD ESMAILI |
| Issued | 7/2/2021 | APPLICANT |
| CofO in Progress | 1/18/2024 | WILLIAM WREN |
| CofO in Progress | 1/18/2024 | WILLIAM WREN |
| CofO in Progress | 1/18/2024 | WILLIAM WREN |
| CofO in Progress | 1/31/2024 | DAVID MATSON |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/24/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2020 | WALLIE JONG |
| Sewer availability | Cleared | 9/25/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 10/8/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/8/2021 | SARAH YOUSSEF |
| Grading Pre-Inspection | Cleared | 1/21/2021 | MANUEL TEJADA |
| Roof/Waste drainage to street | Cleared | 2/2/2021 | WALLIE JONG |
| ZI | Cleared | 2/2/2021 | ANACANY HURTADO |
| GPI Written Notices | Cleared | 5/12/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/25/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 9/10/2021 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/10/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/7/2021 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/4/2022 | Approved | MATTHEW NELSON |
| HVAC-Rough | 2/4/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 2/4/2022 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2022 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 3/15/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/24/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/24/2022 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 3/24/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/6/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 4/6/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 4/18/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 4/18/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/27/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 5/17/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 5/17/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/7/2022 | Partial Approval | MATTHEW NELSON |
| Gas Test | 10/14/2022 | Approved | MATTHEW NELSON |
| Sewer | 10/14/2022 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 10/20/2022 | Approved | MATTHEW NELSON |
| Gas Test | 11/1/2022 | Approved | MATTHEW NELSON |
| Underground Mechanical | 11/1/2022 | Partial Approval | MATTHEW NELSON |
| Service/Power Release | 12/22/2022 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Final | 7/24/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 7/24/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 7/24/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Final | 7/24/2023 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 7/24/2023 | SGSOV Not Ready | WILLIAM WREN |
| Service/Power Release | 7/24/2023 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 7/24/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 7/31/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 7/31/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 7/31/2023 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 7/31/2023 | No Access for Inspection | WILLIAM WREN |
| Final | 8/14/2023 | Corrections Issued | WILLIAM WREN |
| Service/Power Release | 8/14/2023 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 8/14/2023 | Approved | WILLIAM WREN |
| Final | 8/17/2023 | Corrections Issued | WILLIAM WREN |
| Final | 9/8/2023 | Corrections Issued | WILLIAM WREN |
| Service/Power Release | 9/8/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 11/1/2023 | Not Ready for Inspection | WILLIAM WREN |
| Gas Test | 11/1/2023 | Approved | WILLIAM WREN |
| Service/Power Release | 11/1/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 11/16/2023 | Corrections Issued | WILLIAM WREN |
| Service/Power Release | 11/16/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 1/8/2024 | OK to Issue CofO | WILLIAM WREN |
| Service/Power Release | 1/8/2024 | Approved | WILLIAM WREN |