13878 W RAYEN ST 91331
Certificate Information: 13878 W RAYEN ST 91331
- Application / Permit
- 20010-20000-02186
- Plan Check / Job No.
- B20VN08605
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY ADU PER LAMC 12.22 A.33(c) AND (d) W/ATT PATIO COVER
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | JESSE ARELLANO |
| Corrections Issued | 7/25/2020 | JESSE ARELLANO |
| Quality Review Completed | 7/30/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 1/27/2021 | JESSE ARELLANO |
| Plan Check Approved | 2/2/2021 | JESSE ARELLANO |
| Issued | 3/17/2021 | APPLICANT |
| Building Plans Picked Up | 3/22/2021 | APPLICANT |
| CofO in Progress | 2/23/2022 | GREGG CUMMINGS |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/7/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 11/10/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/1/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/17/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
| Green Code | Cleared | 2/2/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/12/2021 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 4/26/2021 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/3/2021 | Partial Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 5/3/2021 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 5/3/2021 | Partial Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 6/22/2021 | Corrections Issued | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 6/24/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/6/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 7/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 7/6/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 7/6/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/6/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/6/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 7/6/2021 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 7/6/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 7/6/2021 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 7/6/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 7/9/2021 | No Access for Inspection | GREGG CUMMINGS |
| Insulation | 7/9/2021 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/13/2021 | Approved | GREGG CUMMINGS |
| Insulation | 7/13/2021 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/13/2021 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 7/13/2021 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 7/23/2021 | Approved | ALAN MORELOS |
| Shower Pan | 7/23/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 8/9/2021 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 8/20/2021 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/4/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 11/4/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/4/2021 | Approved | GREGG CUMMINGS |
| HVAC-Final | 11/4/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 11/4/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 11/4/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 11/4/2021 | Approved | GREGG CUMMINGS |
| Final | 1/12/2022 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 1/12/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 2/17/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Final | 2/17/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/17/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/17/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 2/17/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/23/2022 | Approved | GREGG CUMMINGS |
| Final | 2/23/2022 | OK to Issue CofO | GREGG CUMMINGS |
| Service/Power Release | 2/23/2022 | Approved | GREGG CUMMINGS |