4533 1/2 N CALEDONIA WAY 90065

Certificate Information: 4533 1/2 N CALEDONIA WAY 90065

Application / Permit
20010-20000-02185
Plan Check / Job No.
B20VN08603
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'-3" X 45'-7" IRREGULAR SHAPE 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d) WITH ATTACHED UNCOVRED DECK PATIO.
Permit Issued
Issued on 5/3/2021
Issuing Office
Valley
Current Status
CofO Issued on 9/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 SERGIO MUNIZ
Corrections Issued 7/27/2020 SERGIO MUNIZ
Quality Review Completed 9/1/2020 OMID HEDAYAT
Applicant returned to address corrections 3/9/2021 SERGIO MUNIZ
Applicant returned to address corrections 4/13/2021 SERGIO MUNIZ
Plan Check Approved 4/20/2021 SERGIO MUNIZ
Building Plans Picked Up 4/26/2021 APPLICANT
Issued 5/3/2021 APPLICANT
CofO in Progress 8/27/2022 CRAIG VAUGHAN
Permit Finaled 9/2/2022 DEROLD HAUFF
CofO Issued 9/2/2022 DEROLD HAUFF
Permit Finaled 9/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/28/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/29/2020 WALLIE JONG
Miscellaneous Cleared 9/29/2020 WALLIE JONG
Sewer availability Cleared 9/29/2020 WALLIE JONG
Hydrant and Access approval Cleared 12/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 2/24/2021 ORVAL HERNANDEZ-MARCI
Grading Pre-Inspection Cleared 3/9/2021 SERGIO MUNIZ
Roof/Waste drainage to street Cleared 3/23/2021 ROSA SILVA
Supp. Use District POD/CDO/TDO Cleared 3/25/2021 ADRINEH MELKONIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Kazarians,, Ardashes; Lic. No.: C36687 1528 CANADA BLVD STE 206      GLENDALE, CA 91208

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/12/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/28/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/8/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 9/8/2021 Partial Approval CRAIG VAUGHAN
Insulation 9/16/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/26/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 10/26/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 10/26/2021 Approved CRAIG VAUGHAN
HVAC-Rough 10/26/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 10/26/2021 Approved CRAIG VAUGHAN
Verify Sprinkler Sign Off 10/26/2021 Approved CRAIG VAUGHAN
Deputy Wood Construction 10/28/2021 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/29/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/29/2021 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 11/29/2021 Approved CRAIG VAUGHAN
Drywall Nailing 12/10/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 12/10/2021 Approved CRAIG VAUGHAN
Insulation 12/10/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 12/10/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 1/3/2022 Partial Approval CHRIS CHRISTENSEN
Shower Pan 1/3/2022 Approved CHRIS CHRISTENSEN
Sewer 4/1/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 4/21/2022 Partial Approval CRAIG VAUGHAN
Underground Mechanical 4/28/2022 Partial Approval SCOTT FINNILA
Gas Test 5/10/2022 Approved HAMIK HARTOUNIAN
Final 8/18/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/18/2022 Approved CRAIG VAUGHAN
Green Building Final 8/18/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 8/18/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 8/18/2022 Not Ready for Inspection CRAIG VAUGHAN
Final 8/24/2022 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 8/24/2022 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 8/24/2022 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 8/26/2022 Approved CRAIG VAUGHAN
Final 8/26/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 8/26/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 8/26/2022 Approved CRAIG VAUGHAN
Service/Power Release 8/26/2022 Approved CRAIG VAUGHAN
Smoke Detectors 8/26/2022 Approved CRAIG VAUGHAN