11254 W VALLEY SPRING LANE 91602

Certificate Information: 11254 W VALLEY SPRING LANE 91602

Application / Permit
20010-20000-02177
Plan Check / Job No.
B20VN08559
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 13'5"X35'4" 2-STORY ADU
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 MARVEL DELACRUZ
Corrections Issued 7/25/2020 MARVEL DELACRUZ
Quality Review Completed 7/31/2020 STEVEN KIM
Building Plans Picked Up 8/4/2020 APPLICANT
Applicant returned to address corrections 11/5/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/3/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/15/2020 MARVEL DELACRUZ
Plan Check Approved 12/17/2020 MARVEL DELACRUZ
Issued 12/30/2020 APPLICANT
CofO in Progress 10/26/2022 JACK KARGODORIAN
Permit Finaled 1/14/2023 MICHAEL SMITH
CofO Issued 1/14/2023 MICHAEL SMITH
Permit Finaled 1/14/2023 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 8/14/2020 STEVEN WECHSLER
Address approval Cleared 8/26/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/27/2020 ADRIAN CASTRO
Sewer availability Cleared 8/27/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 9/16/2020 KURT CORRAL
Low Impact Development Cleared 10/19/2020 MITESH PATEL
Construction near power lines Cleared 11/23/2020 OSCAR CASTRO
Construction within easement Cleared 11/23/2020 OSCAR CASTRO
Roof/Waste drainage to street Cleared 11/30/2020 ADRIAN CASTRO
Green Code Cleared 12/17/2020 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/7/2021 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 1/15/2021 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 1/21/2021 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Corrections Issued THOMAS FINNILA
Special/Order Compliance 2/3/2021 Approved THOMAS FINNILA
PLUMBING-Rough 3/19/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 3/22/2021 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 3/24/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 3/30/2021 No Access for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/7/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/13/2021 Approved ARAM AVEDISIAN
Sewer 5/13/2021 Approved ARAM AVEDISIAN
Deputy Wood Construction 7/15/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 7/30/2021 No Access for Inspection THOMAS FINNILA
HVAC-Rough 7/30/2021 No Access for Inspection THOMAS FINNILA
Wood Frame 7/30/2021 No Access for Inspection THOMAS FINNILA
ELECTRICAL-Rough 8/3/2021 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 8/3/2021 Not Ready for Inspection THOMAS FINNILA
Verify Sprinkler Sign Off 8/3/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 8/3/2021 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 8/23/2021 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 8/27/2021 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 9/1/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 9/1/2021 Conditional Approval THOMAS FINNILA
Green Building Rough 9/1/2021 Approved THOMAS FINNILA
HVAC-Rough 9/1/2021 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 9/1/2021 Conditional Approval THOMAS FINNILA
Insulation 9/14/2021 Not Ready for Inspection JUSTIN HAWLEY
Insulation 9/15/2021 Conditional Approval JUSTIN HAWLEY
Insulation 9/16/2021 Approved JUSTIN HAWLEY
Insulation 9/17/2021 Approved JUSTIN HAWLEY
Drywall Nailing 9/27/2021 Approved THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/29/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 7/6/2022 Approved MATT KELLERMAN
ELECTRICAL-Final 7/6/2022 Corrections Issued MATT KELLERMAN
Final 7/6/2022 Corrections Issued MATT KELLERMAN
Green Building Final 7/6/2022 Approved MATT KELLERMAN
HVAC-Final 7/6/2022 Corrections Issued MATT KELLERMAN
PLUMBING-Final 7/6/2022 Corrections Issued MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Not Ready MATT KELLERMAN
Service/Power Release 7/6/2022 Corrections Issued MATT KELLERMAN
Smoke Detectors 7/6/2022 Approved MATT KELLERMAN
Verify Sprinkler Sign Off 7/6/2022 Approved MATT KELLERMAN
Final 8/8/2022 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 8/25/2022 Not Ready for Inspection THOMAS FINNILA
Final 8/25/2022 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 8/25/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 9/14/2022 Approved THOMAS FINNILA
Final 9/14/2022 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 9/14/2022 Approved THOMAS FINNILA
PLUMBING-Final 9/14/2022 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Approved THOMAS FINNILA
Service/Power Release 9/14/2022 Not Ready for Inspection THOMAS FINNILA
Service/Power Release 9/23/2022 Corrections Issued THOMAS FINNILA
Final 10/25/2022 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 10/25/2022 Approved JACK KARGODORIAN