8434 N OUTLAND VIEW DR 91352
Certificate Information: 8434 N OUTLAND VIEW DR 91352
- Application / Permit
- 20010-20000-02172
- Plan Check / Job No.
- B20VN08539
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 51'6" X 23'3-3/4" ONE STORY DETACHED ACCESSORY DWELLING UNIT WITH ATTACHED TWO CAR GARAGE AND STORAGE ROOM, NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/27/2021
- Issuing Office
- Current Status
- CofO Issued on 6/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | RARES BODEA |
| Corrections Issued | 8/12/2020 | RARES BODEA |
| Quality Review Completed | 8/14/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/17/2020 | APPLICANT |
| Applicant returned to address corrections | 1/20/2021 | RARES BODEA |
| Plan Check Approved | 4/6/2021 | RARES BODEA |
| Issued | 4/27/2021 | APPLICANT |
| CofO in Progress | 6/14/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 6/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/15/2020 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 9/15/2020 | ADRIAN CASTRO |
| Street Frontage | Cleared | 9/15/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/16/2020 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 9/18/2020 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 9/18/2020 | RARES BODEA |
| Hydrant and Access approval | Cleared | 9/30/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 1/5/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 4/5/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/5/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
| Engineer | Azarmy,, Cyrus; Lic. No.: L9404 | 20206 ARCHWOOD ST WINNETKA, CA 91306 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2021 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 6/3/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/9/2021 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 6/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/15/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 6/15/2021 | Partial Approval | GREGG CUMMINGS |
| Deputy Reinf. Concrete | 6/22/2021 | Conditional Approval | DAVID MATSON |
| Insulation | 6/22/2021 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 6/22/2021 | Partial Approval | JOHN HAYES |
| Wood Frame | 6/22/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 7/27/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 7/27/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| MERV13>=Rough | 7/27/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 7/27/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Wood Frame | 7/27/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 8/16/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| ELECTRICAL-Rough | 8/16/2021 | Approved | WILLIAM KUEHN |
| Gas Test | 8/16/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 8/16/2021 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 8/16/2021 | Approved | WILLIAM KUEHN |
| MERV13>=Rough | 8/16/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 8/16/2021 | Approved | WILLIAM KUEHN |
| Sewer | 8/16/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Underground Mechanical | 8/16/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 8/16/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Wood Frame | 8/16/2021 | Approved | WILLIAM KUEHN |
| Sewer | 8/18/2021 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 8/18/2021 | Partial Inspection | WILLIAM KUEHN |
| Insulation | 9/8/2021 | Conditional Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/8/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 9/10/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/10/2021 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 9/21/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/21/2021 | Partial Inspection | WILLIAM KUEHN |
| Shower Pan | 9/21/2021 | Approved | WILLIAM KUEHN |
| Final | 12/30/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Green Building Final | 12/30/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/30/2021 | SGSOV Not Ready | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/4/2022 | Corrections Issued | DAVID MATSON |
| HVAC-Final | 1/4/2022 | Corrections Issued | DAVID MATSON |
| PLUMBING-Final | 1/4/2022 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 4/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 4/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/20/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 4/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 4/22/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 4/22/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/22/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 4/22/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/27/2022 | Corrections Issued | MATTHEW NELSON |
| Final | 5/27/2022 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 5/27/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 6/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/2/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 6/2/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 6/14/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 6/14/2022 | Approved | CHRISTOPHER DELLEFIELD |