13169 N PHILLIPPI AVE 91342

Certificate Information: 13169 N PHILLIPPI AVE 91342

Application / Permit
20010-20000-02149
Plan Check / Job No.
B20VN08423
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 48'-6" X 29'-6" DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A33.
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 SERGIO MUNIZ
Corrections Issued 7/24/2020 SERGIO MUNIZ
Quality Review Completed 8/5/2020 OMID HEDAYAT
Building Plans Picked Up 8/5/2020 APPLICANT
Applicant returned to address corrections 11/17/2020 SERGIO MUNIZ
Applicant returned to address corrections 12/12/2020 SERGIO MUNIZ
Plan Check Approved 1/12/2021 SERGIO MUNIZ
Issued 1/27/2021 APPLICANT
CofO in Progress 9/17/2021 JOHN HAYES
Permit Finaled 3/16/2022 RONALD MYRICK
CofO Issued 3/16/2022 RONALD MYRICK
Permit Finaled 3/16/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/18/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/18/2020 ADRIAN CASTRO
Sewer availability Cleared 8/18/2020 ADRIAN CASTRO
Tract Map conditions Cleared 8/18/2020 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 10/26/2020 KURT CORRAL
Low Impact Development Cleared 10/27/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/19/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Muradyan,, David; Lic. No.: S6232 10233 JOHANNA AVE      SUNLAND, CA 91040

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/23/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 3/23/2021 Partial Approval MISAEL ESPARZA
Pre-Inspection 3/23/2021 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/1/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 4/1/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/29/2021 Corrections Issued MISAEL ESPARZA
Wood Frame 4/29/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 5/21/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/21/2021 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 5/21/2021 Approved MICHEL ABAJAN
HVAC-Rough 5/21/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 5/21/2021 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 5/21/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/3/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 6/3/2021 Partial Approval MISAEL ESPARZA
Shower Pan 6/3/2021 Not Ready for Inspection MISAEL ESPARZA
Insulation 6/9/2021 Corrections Issued MISAEL ESPARZA
Sewer 6/15/2021 Corrections Issued MISAEL ESPARZA
Underground Mechanical 6/15/2021 Partial Approval MISAEL ESPARZA
Insulation 6/18/2021 Approved MISAEL ESPARZA
Sewer 6/18/2021 Partial Approval MISAEL ESPARZA
Shower Pan 6/18/2021 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 6/28/2021 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/6/2021 Corrections Issued MISAEL ESPARZA
Shower Pan 7/6/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/12/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 7/12/2021 Approved MISAEL ESPARZA
Final 9/9/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 9/9/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 9/9/2021 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 9/9/2021 Approved MISAEL ESPARZA
Final 9/15/2021 Corrections Issued JOHN HAYES
Green Building Final 9/15/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 9/15/2021 Not Ready for Inspection JOHN HAYES
Final 9/16/2021 OK to Issue CofO JOHN HAYES
Green Building Final 9/16/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved JOHN HAYES
Service/Power Release 9/16/2021 Approved JOHN HAYES