22352 1/2 W SCHOENBORN ST 91304
Certificate Information: 22352 1/2 W SCHOENBORN ST 91304
- Application / Permit
- 20010-20000-02148
- Plan Check / Job No.
- B20VN08417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 38' X 27' AND 13'-6" X 12'-8" ADDITION TO THE (E) DETACHED GARAGE AND CONVERT TO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A33. WORK DONE PER WFPP .
- Permit Issued
- Issued on 11/8/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2020 | SERGIO MUNIZ |
| Corrections Issued | 7/1/2020 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/1/2020 | APPLICANT |
| Applicant returned to address corrections | 5/21/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/22/2022 | SERGIO MUNIZ |
| Applicant returned to address corrections | 11/2/2022 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 11/8/2022 | MIROOSH KHACHATOORIAN |
| Issued | 11/8/2022 | APPLICANT |
| CofO in Progress | 7/23/2025 | JEFFREY HARTLINE |
| Permit Finaled | 8/5/2025 | DANIEL ORRANTE |
| CofO Issued | 8/5/2025 | DANIEL ORRANTE |
| Permit Finaled | 8/5/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/26/2021 | BRIAN MILLER |
| Address approval | Cleared | 3/30/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/31/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 3/2/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/23/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 4/21/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/11/2023 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 6/28/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/12/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 1/26/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 5/6/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/29/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 5/29/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/11/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 6/11/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/15/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/17/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 8/2/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 8/2/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/2/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 9/5/2024 | No Access for Inspection | GEVORK IPCHYAN |
| Insulation | 9/9/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 9/18/2024 | Approved | JEFFREY HARTLINE |
| Insulation | 9/18/2024 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 9/18/2024 | Partial Approval | JEFFREY HARTLINE |
| Final | 6/3/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 6/3/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 6/3/2025 | SGSOV Not Required | JEFFREY HARTLINE |
| Smoke Detectors | 6/3/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 6/16/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Final | 6/16/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 6/16/2025 | Approved | JEFFREY HARTLINE |
| Final | 6/25/2025 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 6/25/2025 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 6/25/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 7/22/2025 | OK to Issue CofO | JEFFREY HARTLINE |
| Service/Power Release | 7/22/2025 | Approved | JEFFREY HARTLINE |