16757 W RAYEN ST 91343
Certificate Information: 16757 W RAYEN ST 91343
- Application / Permit
- 20010-20000-02138
- Plan Check / Job No.
- B20VN08382
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT AND TRELLIS AND POOL BATH (48'-6"X20'-7") PER LAMC 12.22 A.33(c)¹, (d)¹, and (g) fire sprinklers nfpa 13D
- Permit Issued
- Issued on 12/18/2020
- Issuing Office
- Current Status
- CofO Issued on 7/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/1/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/7/2020 | MOHAMMAD ESMAILI |
| Issued | 12/18/2020 | APPLICANT |
| Building Plans Picked Up | 12/23/2020 | APPLICANT |
| CofO in Progress | 7/11/2025 | JOAQUIN GREENOUGH |
| Permit Finaled | 7/11/2025 | RUBEN SALAS |
| CofO Issued | 7/11/2025 | RUBEN SALAS |
| Permit Finaled | 7/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/29/2020 | WALTER RAMIREZ |
| Disturb/Remove Protected Trees | Cleared | 9/30/2020 | MOHAMMAD ESMAILI |
| Address approval | Cleared | 10/1/2020 | ADRIAN CASTRO |
| Certificate of Compliance | Cleared | 10/1/2020 | MARC WOERSCHING |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | ADRIAN CASTRO |
| Miscellaneous | Cleared | 10/1/2020 | MARC WOERSCHING |
| Sewer availability | Cleared | 10/1/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 10/26/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 11/24/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 12/4/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Grid Line Structures Inc; Lic. No.: 1070999-B | 5304 1/2 LA MIRADA AVE LOS ANGELES, CA 90029 |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/1/2021 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 3/11/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/19/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 3/19/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/20/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 5/6/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 5/10/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Partial Approval | ARTHUR SARGSYAN |
| Green Building Rough | 5/12/2021 | Approved | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 5/12/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 5/12/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 12/6/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 12/13/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 12/23/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 3/16/2023 | Approved | RAUL OLAGI |
| Shower Pan | 3/16/2023 | Approved | RAUL OLAGI |
| Sewer | 7/27/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 7/27/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 12/2/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 12/13/2024 | Approved | RAUL OLAGI |
| Final | 12/13/2024 | Corrections Issued | RAUL OLAGI |
| Gas Test | 12/13/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 12/13/2024 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 12/13/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 1/28/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 2/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 2/21/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| Final | 6/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 6/26/2025 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 6/26/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Final | 7/10/2025 | OK to Issue CofO | JOAQUIN GREENOUGH |