Pre-Inspection
|
1/5/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Piling/Pier/Caisson
|
1/26/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
2/2/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
FLOOD-Elevation Certificate
|
2/16/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
2/16/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Underground Mechanical
|
2/16/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
3/5/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Piling/Pier/Caisson
|
3/22/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
4/26/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
FLOOD-Elevation Certificate
|
4/26/2021
|
Approved
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
4/26/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
4/29/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
4/30/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
5/3/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Shotcrete
|
5/4/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
5/6/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
5/19/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
5/24/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
5/24/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
FLOOD-Proofing Certificate
|
5/24/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
5/24/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
5/24/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
FLOOD-Proofing Certificate
|
5/28/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/28/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
5/28/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
5/28/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
6/3/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Underground Mechanical
|
7/20/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
7/27/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
8/9/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
8/10/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
9/1/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Reinf. Concrete
|
9/3/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
9/7/2021
|
Conditional Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
9/8/2021
|
Approved
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
9/28/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
9/29/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
9/30/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
10/1/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
10/8/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
10/22/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/22/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Steel/Welding
|
10/27/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/23/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Wood Construction
|
12/1/2021
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/3/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/8/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Sewer
|
1/21/2022
|
Approved
|
DEANDRE HOFFMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/14/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
4/25/2022
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Shower Pan
|
4/28/2022
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
PLUMBING-Rough
|
4/29/2022
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Shower Pan
|
4/29/2022
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
5/10/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
HVAC-Rough
|
5/12/2022
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
5/23/2022
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Wood Construction
|
6/1/2022
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/3/2022
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/7/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
BUILDING-Rough-Frame
|
6/29/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
FLOOD-Proofing Certificate
|
6/29/2022
|
Approved
|
BRENDAN LOONEY
|
|
Green Building Rough
|
6/29/2022
|
Approved
|
BRENDAN LOONEY
|
|
Verify Sprinkler Sign Off
|
6/29/2022
|
Approved
|
BRENDAN LOONEY
|
|
BUILDING-Rough-Frame
|
7/13/2022
|
Approved
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Rough
|
7/13/2022
|
Approved
|
STEPHANIE SWANSON
|
|
HVAC-Rough
|
7/13/2022
|
Approved
|
STEPHANIE SWANSON
|
|
Insulation
|
7/13/2022
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Insulation
|
7/20/2022
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Drywall Nailing
|
8/4/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
8/17/2022
|
Approved
|
ANDREW NAVE
|
|
Underground Mechanical
|
8/17/2022
|
Partial Approval
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
10/3/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Steel/Welding
|
2/1/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Steel/Welding
|
2/3/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Steel/Welding
|
2/6/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Steel/Welding
|
2/7/2023
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Gas Test
|
2/27/2023
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Special/Order Compliance
|
2/27/2023
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
HVAC-Final
|
11/27/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
ELECTRICAL-Final
|
12/13/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
ELECTRICAL-Final
|
12/20/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
PLUMBING-Final
|
12/20/2023
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Final
|
1/30/2024
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
1/30/2024
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Green Building Final
|
1/30/2024
|
Approved
|
BRENDAN LOONEY
|
|
Reinforced Concrete Frame
|
1/30/2024
|
Approved
|
BRENDAN LOONEY
|
|
SGSOV-Seismic Gas S/O Valve
|
1/30/2024
|
SGSOV Not Ready
|
BRENDAN LOONEY
|
|
Service/Power Release
|
1/30/2024
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Smoke Detectors
|
1/30/2024
|
Approved
|
BRENDAN LOONEY
|
|
Final
|
2/1/2024
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
2/1/2024
|
Approved
|
BRENDAN LOONEY
|
|
SGSOV-Seismic Gas S/O Valve
|
2/1/2024
|
SGSOV Approved
|
BRENDAN LOONEY
|
|
Service/Power Release
|
2/1/2024
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Special/Order Compliance
|
2/1/2024
|
Partial Inspection
|
BEN MOLSTAD
|
|
Final
|
2/7/2024
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Service/Power Release
|
2/7/2024
|
Approved
|
BRENDAN LOONEY
|
|
Final
|
2/20/2024
|
OK to Issue CofO
|
MICHAEL PELHAM
|