16350 W BALLINGER ST 91343

Certificate Information: 16350 W BALLINGER ST 91343

Application / Permit
20010-20000-02096
Plan Check / Job No.
B20VN08259
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 31'-6" X 19'-1"IRREGULAR SHAPE 2-STORY DETACHED ACCESSORY DWELLING UNIT PER STATE ORDINANCE 186,481.
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 SERGIO MUNIZ
Corrections Issued 7/23/2020 SERGIO MUNIZ
Quality Review Completed 8/11/2020 OMID HEDAYAT
Building Plans Picked Up 8/12/2020 APPLICANT
Applicant returned to address corrections 11/7/2020 SERGIO MUNIZ
Applicant returned to address corrections 2/23/2021 SERGIO MUNIZ
Plan Check Approved 2/24/2021 SERGIO MUNIZ
Issued 3/23/2021 APPLICANT
CofO in Progress 8/16/2022 DEANDRE HOFFMAN
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Issued 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/12/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/13/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 10/22/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/12/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 11/24/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 2/23/2021 SERGIO MUNIZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/7/2021 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 9/16/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Partial Approval RAUL OLAGI
Deputy Wood Construction 12/6/2021 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 12/22/2021 Approved VINCENT HANLEY
PLUMBING-Rough 12/22/2021 Approved VINCENT HANLEY
Sewer 12/22/2021 Approved VINCENT HANLEY
Wood Frame 12/22/2021 Not Ready for Inspection VINCENT HANLEY
Gas Test 2/10/2022 Approved MICHAEL TEMPLE
Underground Mechanical 2/10/2022 Approved MICHAEL TEMPLE
HVAC-Rough 2/25/2022 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 2/25/2022 Not Ready for Inspection RAUL OLAGI
Wood Frame 2/25/2022 Corrections Issued RAUL OLAGI
HVAC-Rough 3/2/2022 Corrections Issued RAUL OLAGI
Interior/Exterior Lathing 3/2/2022 Partial Approval RAUL OLAGI
Wood Frame 3/2/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 3/8/2022 Conditional Approval RAUL OLAGI
Green Building Rough 3/8/2022 Approved RAUL OLAGI
HVAC-Rough 3/8/2022 Approved RAUL OLAGI
Insulation 3/15/2022 Approved ALAN MORELOS
Drywall Nailing 3/21/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 4/13/2022 Corrections Issued DEANDRE HOFFMAN
Shower Pan 4/13/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 4/20/2022 Approved ALAN MORELOS
BUILDING-Rough-Frame 7/13/2022 Approved ALAN MORELOS
ELECTRICAL-Final 7/13/2022 Approved ALAN MORELOS
Final 7/13/2022 Corrections Issued ALAN MORELOS
Green Building Final 7/13/2022 Approved ALAN MORELOS
HVAC-Final 7/13/2022 Corrections Issued ALAN MORELOS
PLUMBING-Final 7/13/2022 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Not Ready ALAN MORELOS
Service/Power Release 7/13/2022 Not Ready for Inspection ALAN MORELOS
Smoke Detectors 7/13/2022 Approved ALAN MORELOS
Verify Sprinkler Sign Off 7/13/2022 Approved ALAN MORELOS
Final 7/20/2022 Not Ready for Inspection DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Approved DEANDRE HOFFMAN
Service/Power Release 7/20/2022 Not Ready for Inspection DEANDRE HOFFMAN
Final 8/2/2022 Conditional Approval DEANDRE HOFFMAN
Service/Power Release 8/2/2022 Approved DEANDRE HOFFMAN