16350 W BALLINGER ST 91343
Certificate Information: 16350 W BALLINGER ST 91343
- Application / Permit
- 20010-20000-02096
- Plan Check / Job No.
- B20VN08259
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 31'-6" X 19'-1"IRREGULAR SHAPE 2-STORY DETACHED ACCESSORY DWELLING UNIT PER STATE ORDINANCE 186,481.
- Permit Issued
- Issued on 3/23/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | SERGIO MUNIZ |
| Corrections Issued | 7/23/2020 | SERGIO MUNIZ |
| Quality Review Completed | 8/11/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 8/12/2020 | APPLICANT |
| Applicant returned to address corrections | 11/7/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 2/23/2021 | SERGIO MUNIZ |
| Plan Check Approved | 2/24/2021 | SERGIO MUNIZ |
| Issued | 3/23/2021 | APPLICANT |
| CofO in Progress | 8/16/2022 | DEANDRE HOFFMAN |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
| CofO Issued | 8/27/2022 | DEROLD HAUFF |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/13/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 10/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/12/2020 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 11/24/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 2/23/2021 | SERGIO MUNIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/7/2021 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/16/2021 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | RAUL OLAGI |
| Deputy Wood Construction | 12/6/2021 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2021 | Partial Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 12/22/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/22/2021 | Approved | VINCENT HANLEY |
| Sewer | 12/22/2021 | Approved | VINCENT HANLEY |
| Wood Frame | 12/22/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Gas Test | 2/10/2022 | Approved | MICHAEL TEMPLE |
| Underground Mechanical | 2/10/2022 | Approved | MICHAEL TEMPLE |
| HVAC-Rough | 2/25/2022 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 2/25/2022 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 2/25/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 3/2/2022 | Corrections Issued | RAUL OLAGI |
| Interior/Exterior Lathing | 3/2/2022 | Partial Approval | RAUL OLAGI |
| Wood Frame | 3/2/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/8/2022 | Conditional Approval | RAUL OLAGI |
| Green Building Rough | 3/8/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 3/8/2022 | Approved | RAUL OLAGI |
| Insulation | 3/15/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 3/21/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/13/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Shower Pan | 4/13/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 4/20/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/13/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 7/13/2022 | Approved | ALAN MORELOS |
| Final | 7/13/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Final | 7/13/2022 | Approved | ALAN MORELOS |
| HVAC-Final | 7/13/2022 | Corrections Issued | ALAN MORELOS |
| PLUMBING-Final | 7/13/2022 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Not Ready | ALAN MORELOS |
| Service/Power Release | 7/13/2022 | Not Ready for Inspection | ALAN MORELOS |
| Smoke Detectors | 7/13/2022 | Approved | ALAN MORELOS |
| Verify Sprinkler Sign Off | 7/13/2022 | Approved | ALAN MORELOS |
| Final | 7/20/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2022 | SGSOV Approved | DEANDRE HOFFMAN |
| Service/Power Release | 7/20/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 8/2/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Service/Power Release | 8/2/2022 | Approved | DEANDRE HOFFMAN |