10542 N PINYON AVE 91042

Certificate Information: 10542 N PINYON AVE 91042

Application / Permit
20010-20000-02055
Plan Check / Job No.
B20VN08092
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 23' x 18' DETACHED ACCESSORY DWELLING UNIT
Permit Issued
Issued on 8/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2020 APPLICANT
Assigned to Plan Check Engineer 7/9/2020 SELLA BENYAMIN
Corrections Issued 7/10/2020 SELLA BENYAMIN
Quality Review Completed 7/16/2020 STEVEN KIM
Building Plans Picked Up 7/16/2020 APPLICANT
Plan Check Approved 8/14/2020 SELLA BENYAMIN
Issued 8/24/2020 APPLICANT
CofO in Progress 4/9/2021 MATTHEW NELSON
Permit Finaled 7/24/2021 MICHAEL SMITH
CofO Issued 7/24/2021 MICHAEL SMITH
Permit Finaled 7/24/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/20/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 7/20/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/21/2020 GABRIEL ROBLES
Sewer availability Cleared 7/21/2020 GABRIEL ROBLES

Contact Information

No Data Available.

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/8/2020 Partial Inspection MATTHEW NELSON
Footing/Foundation/Slab 9/10/2020 Approved DAVID MATSON
ELECTRICAL-Rough 10/5/2020 Approved MATTHEW NELSON
PLUMBING-Rough 10/5/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/7/2020 Approved MATTHEW NELSON
Green Building Rough 10/7/2020 Approved MATTHEW NELSON
HVAC-Rough 10/7/2020 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 10/7/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/15/2020 Approved MATTHEW NELSON
Drywall Nailing 10/19/2020 Approved MATTHEW NELSON
Insulation 10/19/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/19/2020 Approved MATTHEW NELSON
Shower Pan 10/19/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 3/18/2021 Approved MATTHEW NELSON
Final 3/18/2021 Corrections Issued MATTHEW NELSON
Green Building Final 3/18/2021 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/18/2021 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 3/18/2021 Approved MATTHEW NELSON
Final 3/25/2021 Corrections Issued MATTHEW NELSON
Green Building Final 3/25/2021 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved MATTHEW NELSON
Service/Power Release 3/25/2021 Approved MATTHEW NELSON
Final 4/9/2021 OK to Issue CofO MATTHEW NELSON
Green Building Final 4/9/2021 Approved MATTHEW NELSON
HVAC-Final 4/9/2021 Approved MATTHEW NELSON
PLUMBING-Final 4/9/2021 Approved MATTHEW NELSON