4447 N CAMELLIA AVE 91602
Certificate Information: 4447 N CAMELLIA AVE 91602
- Application / Permit
- 20010-20000-02048
- Plan Check / Job No.
- B20VN08042
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD/GARAGE ( 68'-3"x40'-6") fully sprinklers NFPA-13D
- Permit Issued
- Issued on 10/4/2021
- Issuing Office
- Current Status
- CofO Issued on 5/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/13/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 8/11/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 8/12/2020 | APPLICANT |
| Applicant returned to address corrections | 9/8/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 10/4/2021 | MOHAMMAD ESMAILI |
| Issued | 10/4/2021 | APPLICANT |
| CofO in Progress | 2/14/2024 | KIRK SANDERS |
| Permit Finaled | 5/8/2024 | RUBEN SALAS |
| CofO Issued | 5/8/2024 | RUBEN SALAS |
| Permit Finaled | 5/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/24/2020 | GUILLERMO PETRA |
| ZA Case | Cleared | 12/1/2020 | DANG NGUYEN |
| ZI | Cleared | 12/8/2020 | LAUREN PADICK |
| Trees in Parkway | Cleared | 12/22/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/30/2020 | ROBERT DUFF |
| Miscellaneous | Cleared | 5/24/2021 | LAUREN PADICK |
| Tract Map conditions | Cleared | 5/24/2021 | LAUREN PADICK |
| Address approval | Cleared | 7/16/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 8/23/2021 | YVAINNE GALSIM |
| Permit | Cleared | 8/24/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/24/2021 | DAGOVERTO GUERRERO |
| Hold | Cleared | 10/18/2021 | JAZELLE A TRINIDAD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/7/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Underground Mechanical | 10/7/2021 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/21/2021 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/1/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 1/10/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/12/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 1/12/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 1/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 1/18/2022 | Approved | MATT KELLERMAN |
| Insulation | 1/21/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 1/21/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/26/2022 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 1/31/2022 | Approved | THOMAS FINNILA |
| Gas Test | 4/8/2022 | Approved | THOMAS FINNILA |
| Gas Test | 4/20/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/18/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Final | 7/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 7/18/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/18/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 7/18/2022 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 7/18/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 7/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 7/26/2022 | Approved | CALEB MEISTER |
| PLUMBING-Final | 7/26/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 12/5/2023 | Approved | KIRK SANDERS |
| Final | 12/5/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 12/5/2023 | Approved | KIRK SANDERS |
| MERV13>=Final | 12/5/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 12/5/2023 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 12/5/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 12/5/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 2/8/2024 | Approved | KIRK SANDERS |
| Final | 2/8/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 2/8/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 2/8/2024 | Approved | KIRK SANDERS |
| Service/Power Release | 2/8/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 2/13/2024 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 2/13/2024 | Approved | KIRK SANDERS |