6833 N ORION AVE 91406

Certificate Information: 6833 N ORION AVE 91406

Application / Permit
20010-20000-02042
Plan Check / Job No.
B20VN08035
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT ( 30'-0"X40'-0") PER LAMC 12.22 A.33(c) and (d) FIRE SPRINKLERS NFPA-13D
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2020 APPLICANT
Assigned to Plan Check Engineer 7/9/2020 MOHAMMAD ESMAILI
Corrections Issued 7/11/2020 MOHAMMAD ESMAILI
Quality Review Completed 8/11/2020 OMID HEDAYAT
Building Plans Picked Up 8/11/2020 APPLICANT
Plan Check Approved 2/11/2021 MOHAMMAD ESMAILI
Issued 2/11/2021 APPLICANT
CofO in Progress 3/23/2023 RYAN SALAZAR
Permit Finaled 4/12/2023 MICHAEL SMITH
CofO Issued 4/12/2023 MICHAEL SMITH
Permit Finaled 4/12/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/9/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 9/9/2020 GABRIEL ROBLES
Sewer availability Cleared 9/9/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/2/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/27/2020 JORGE MEJIA LEMUS
Construction near power lines Cleared 12/15/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 12/18/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/2/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 10/12/2021 Partial Approval RICHARD DOCKUS
Green Building Rough 10/12/2021 Not Ready for Inspection RICHARD DOCKUS
MERV13>=Rough 10/12/2021 Not Ready for Inspection RICHARD DOCKUS
Verify Sprinkler Sign Off 10/12/2021 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 10/18/2021 Approved JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 10/18/2021 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 10/18/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/16/2021 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 11/16/2021 Approved RICHARD DOCKUS
Gas Test 11/16/2021 Corrections Issued RICHARD DOCKUS
Green Building Rough 11/16/2021 Approved RICHARD DOCKUS
HVAC-Rough 11/16/2021 Approved RICHARD DOCKUS
MERV13>=Rough 11/16/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 11/16/2021 Partial Approval RICHARD DOCKUS
Verify Sprinkler Sign Off 11/16/2021 Not Ready for Inspection RICHARD DOCKUS
Gas Test 11/22/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 12/7/2021 Approved RICHARD DOCKUS
Green Building Rough 12/7/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 12/7/2021 Partial Approval RICHARD DOCKUS
Verify Sprinkler Sign Off 12/7/2021 Approved RICHARD DOCKUS
Insulation 12/20/2021 Approved ALAN MORELOS
Drywall Nailing 1/7/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 1/7/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/29/2022 Approved ALAN MORELOS
Shower Pan 3/29/2022 Approved ALAN MORELOS
ELECTRICAL-Final 11/9/2022 Not Ready for Inspection RICHARD DOCKUS
Final 11/9/2022 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 11/9/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Final 11/9/2022 Not Ready for Inspection RICHARD DOCKUS
MERV13>=Final 11/9/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 11/9/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/9/2022 SGSOV Not Ready RICHARD DOCKUS
Service/Power Release 11/9/2022 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 11/9/2022 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Final 11/17/2022 Corrections Issued RICHARD DOCKUS
Gas Test 11/17/2022 Approved RICHARD DOCKUS
HVAC-Final 11/17/2022 Approved RICHARD DOCKUS
Final 11/29/2022 Conditional Approval RYAN SALAZAR
Green Building Final 11/29/2022 Approved RYAN SALAZAR
MERV13>=Final 11/29/2022 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Approved RYAN SALAZAR
Service/Power Release 11/29/2022 Approved RYAN SALAZAR
Smoke Detectors 11/29/2022 Approved RYAN SALAZAR
Final 3/23/2023 OK to Issue CofO RYAN SALAZAR