4638 N TOBIAS AVE 91403
Certificate Information: 4638 N TOBIAS AVE 91403
- Application / Permit
- 20010-20000-02041
- Plan Check / Job No.
- B20VN08030
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT (14'-0"X23'-0") PER LAMC 12.22 A.33(c)¹, (d)¹, and (g) FIRE SPRINKLER NFPA-13D
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/21/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 8/10/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/24/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 2/1/2021 | MOHAMMAD ESMAILI |
| Issued | 3/19/2021 | APPLICANT |
| Building Plans Picked Up | 3/26/2021 | APPLICANT |
| CofO in Progress | 8/12/2022 | MATT KELLERMAN |
| Permit Finaled | 8/12/2022 | RONALD MYRICK |
| CofO Issued | 8/12/2022 | RONALD MYRICK |
| Permit Finaled | 8/12/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Construction within easement | Cleared | 8/17/2020 | RIDWAN HARDY |
| ZI | Cleared | 8/24/2020 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 9/22/2020 | MATTHEW CRAIG |
| Address approval | Cleared | 9/25/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/15/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/12/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/13/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 2828 COCHRAN STREET 321 SIMI VALLEY, CA 93065 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/14/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 8/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 9/27/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 9/27/2021 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/4/2021 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 10/4/2021 | Corrections Issued | MICHAEL PELHAM |
| Green Building Rough | 10/4/2021 | Corrections Issued | MICHAEL PELHAM |
| HVAC-Rough | 10/4/2021 | Approved | MICHAEL PELHAM |
| MERV13>=Rough | 10/4/2021 | Approved | MICHAEL PELHAM |
| Verify Sprinkler Sign Off | 10/4/2021 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Rough | 10/5/2021 | Approved | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/26/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Gas Test | 11/15/2021 | Approved | MISAEL ESPARZA |
| Insulation | 11/16/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/2/2021 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 12/21/2021 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 12/21/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 12/27/2021 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/26/2022 | Corrections Issued | MATT KELLERMAN |
| HVAC-Final | 5/26/2022 | Conditional Approval | MATT KELLERMAN |
| PLUMBING-Final | 5/26/2022 | Corrections Issued | MATT KELLERMAN |
| ELECTRICAL-Final | 6/1/2022 | Conditional Approval | MATT KELLERMAN |
| Gas Test | 6/1/2022 | Approved | MATT KELLERMAN |
| PLUMBING-Final | 6/1/2022 | Approved | MATT KELLERMAN |
| Service/Power Release | 6/1/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | JACK KARGODORIAN |
| Final | 8/3/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/3/2022 | Approved | JACK KARGODORIAN |
| Green Building Final | 8/3/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 8/3/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 8/3/2022 | Approved | JACK KARGODORIAN |
| Final | 8/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 8/10/2022 | Not Ready for Inspection | MATT KELLERMAN |
| MERV13>=Final | 8/10/2022 | Approved | MATT KELLERMAN |
| Final | 8/12/2022 | OK to Issue CofO | MATT KELLERMAN |
| Green Building Final | 8/12/2022 | Approved | MATT KELLERMAN |