7954 N PASO ROBLES AVE 91406
Certificate Information: 7954 N PASO ROBLES AVE 91406
- Application / Permit
- 20010-20000-02023
- Plan Check / Job No.
- B20VN08012
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW DETACHED (43'8"X17'6") ACCESSORY DWELLING UNIT W/ (20'6"X8') ATT PATIO COVER PER ENGR DESIGN.
- Permit Issued
- Issued on 5/6/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 7/13/2020 | HAYATO TSUCHIYA |
| Quality Review Completed | 7/16/2020 | STEVEN KIM |
| Applicant returned to address corrections | 9/11/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/23/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/26/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/30/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/4/2021 | HAYATO TSUCHIYA |
| Issued | 5/6/2021 | APPLICANT |
| Building Plans Picked Up | 5/6/2021 | APPLICANT |
| CofO in Progress | 5/14/2024 | RAUL OLAGI |
| Permit Finaled | 6/5/2024 | RUBEN SALAS |
| Permit Finaled | 6/5/2024 | RUBEN SALAS |
| CofO Issued | 6/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/31/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/1/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 9/16/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/10/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 4/30/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/7/2021 | Corrections Issued | MICHAEL PELHAM |
| PLUMBING-Rough | 6/7/2021 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/10/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/14/2021 | Approved | MICHAEL PELHAM |
| ELECTRICAL-Rough | 8/26/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 8/26/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/26/2021 | Partial Approval | MICHEL ABAJAN |
| Wood Frame | 8/26/2021 | Approved | MICHEL ABAJAN |
| Insulation | 9/20/2021 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 9/20/2021 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 9/20/2021 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 10/1/2021 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/1/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/1/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/5/2021 | Approved | RAUL OLAGI |
| Underground Mechanical | 3/14/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 1/17/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Final | 1/17/2024 | Corrections Issued | RAUL OLAGI |
| Final | 1/17/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 1/17/2024 | Approved | RAUL OLAGI |
| PLUMBING-Final | 1/17/2024 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | RAUL OLAGI |
| Verify Sprinkler Sign Off | 1/17/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/30/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 4/30/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 4/30/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 4/30/2024 | Approved | RAUL OLAGI |
| Smoke Detectors | 4/30/2024 | Approved | RAUL OLAGI |
| Final | 5/3/2024 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 5/3/2024 | Not Ready for Inspection | RAUL OLAGI |
| Final | 5/13/2024 | OK to Issue CofO | RAUL OLAGI |
| HVAC-Final | 5/13/2024 | Approved | RAUL OLAGI |
| Service/Power Release | 5/13/2024 | Approved | RAUL OLAGI |