4475 N MAMMOTH AVE 91423

Certificate Information: 4475 N MAMMOTH AVE 91423

Application / Permit
20010-20000-02021
Plan Check / Job No.
B20VN08001
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 38' X 77'-9" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
CofO Issued on 5/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2020 APPLICANT
Assigned to Plan Check Engineer 7/23/2020 SELLA BENYAMIN
Corrections Issued 7/29/2020 SELLA BENYAMIN
Quality Review Completed 7/31/2020 STEVEN KIM
Building Plans Picked Up 8/6/2020 APPLICANT
Plan Check Approved 3/11/2021 SELLA BENYAMIN
Issued 3/17/2021 APPLICANT
CofO in Progress 4/28/2023 THOMAS FINNILA
CofO in Progress 4/28/2023 THOMAS FINNILA
CofO Issued 5/3/2023 MICHAEL SMITH
Permit Finaled 5/3/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Permit Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/26/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/26/2020 JOHN TRIANTAFYLLOS
Trees in Parkway Cleared 11/16/2020 JOHN KIM
ZI Cleared 12/9/2020 MIGUEL GAMBOA
Low Impact Development Cleared 1/22/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/25/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/10/2021 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/23/2021 Corrections Issued JOHN HAYES
Underground Mechanical 5/3/2021 Approved CHARLES POWELL
Footing/Foundation/Slab 5/13/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Partial Approval CHARLES POWELL
Green Building Rough 6/14/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 6/14/2021 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 8/13/2021 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Partial Approval CHARLES POWELL
Verify Sprinkler Sign Off 8/13/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 9/2/2021 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 9/2/2021 Approved CHARLES POWELL
ELECTRICAL-Rough 10/12/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 10/12/2021 Not Ready for Inspection JOHN HAYES
Shower Pan 11/3/2021 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 11/22/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 11/23/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 11/23/2021 Approved MISAEL ESPARZA
ELECTRICAL-Rough 12/1/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Approved MISAEL ESPARZA
HVAC-Rough 12/3/2021 Approved MISAEL ESPARZA
Shower Pan 12/3/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/7/2021 Approved MISAEL ESPARZA
Green Building Rough 12/7/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 12/7/2021 Approved MISAEL ESPARZA
Insulation 12/17/2021 Partial Approval MISAEL ESPARZA
Pool Piping 12/23/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Drywall Nailing 12/29/2021 Approved THOMAS FINNILA
Green Building Rough 12/29/2021 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 1/5/2022 Partial Approval CALEB MEISTER
Interior/Exterior Lathing 1/11/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 11/21/2022 Approved MISAEL ESPARZA
Gas Test 11/21/2022 Approved MISAEL ESPARZA
Green Building Final 11/21/2022 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 11/21/2022 Approved MISAEL ESPARZA
PLUMBING-Final 11/21/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 11/21/2022 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 11/21/2022 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 12/2/2022 Corrections Issued MISAEL ESPARZA
HVAC-Final 12/20/2022 Approved MISAEL ESPARZA
PLUMBING-Final 12/20/2022 Approved MISAEL ESPARZA
Final 1/10/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 1/10/2023 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 1/10/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 1/10/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 1/24/2023 Corrections Issued MISAEL ESPARZA
Final 3/15/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 3/15/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 3/15/2023 SGSOV Approved MISAEL ESPARZA
Service/Power Release 3/15/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 3/15/2023 Approved MISAEL ESPARZA
Final 3/29/2023 Corrections Issued MISAEL ESPARZA
Service/Power Release 3/29/2023 Not Ready for Inspection MISAEL ESPARZA
Final 4/5/2023 Corrections Issued MISAEL ESPARZA
Service/Power Release 4/5/2023 Not Ready for Inspection MISAEL ESPARZA
Final 4/26/2023 OK to Issue CofO THOMAS FINNILA
Service/Power Release 4/26/2023 Approved THOMAS FINNILA