4471 N MAMMOTH AVE 91423
Certificate Information: 4471 N MAMMOTH AVE 91423
- Application / Permit
- 20010-20000-02019
- Plan Check / Job No.
- B20VN08001
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38' X 77'-9" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 3/17/2021
- Issuing Office
- Current Status
- CofO Issued on 4/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | SELLA BENYAMIN |
| Corrections Issued | 7/29/2020 | SELLA BENYAMIN |
| Quality Review Completed | 7/31/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/6/2020 | APPLICANT |
| Plan Check Approved | 3/11/2021 | SELLA BENYAMIN |
| Issued | 3/17/2021 | APPLICANT |
| CofO in Progress | 4/20/2023 | MISAEL ESPARZA |
| Permit Finaled | 4/27/2023 | MICHAEL SMITH |
| CofO Issued | 4/27/2023 | MICHAEL SMITH |
| Permit Finaled | 4/27/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 10/19/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/26/2020 | JOHN TRIANTAFYLLOS |
| Trees in Parkway | Cleared | 11/16/2020 | JOHN KIM |
| ZI | Cleared | 12/9/2020 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 1/22/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/25/2021 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 2/23/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/4/2021 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 6/14/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 7/14/2021 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | CHARLES POWELL |
| Verify Sprinkler Sign Off | 7/14/2021 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/13/2021 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Partial Approval | CHARLES POWELL |
| Verify Sprinkler Sign Off | 8/13/2021 | Not Ready for Inspection | CHARLES POWELL |
| BUILDING-Rough-Frame | 10/12/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 10/12/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 10/12/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 10/12/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 11/23/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/23/2021 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 11/24/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 11/24/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 11/30/2021 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/2/2021 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/7/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/7/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 12/17/2021 | Partial Approval | MISAEL ESPARZA |
| Pool Piping | 12/23/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Pre-Gunite | 12/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 12/29/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 12/29/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/5/2022 | Partial Approval | CALEB MEISTER |
| Interior/Exterior Lathing | 1/11/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 12/2/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 12/2/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 12/22/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 12/22/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/10/2023 | Approved | MISAEL ESPARZA |
| Final | 1/10/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 1/10/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 1/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 1/10/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 1/24/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 3/29/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 3/29/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 3/29/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 3/29/2023 | Approved | MISAEL ESPARZA |
| Final | 4/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Service/Power Release | 4/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 4/14/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 4/14/2023 | Approved | MISAEL ESPARZA |