13435 W CORCORAN ST 91340

Certificate Information: 13435 W CORCORAN ST 91340

Application / Permit
20010-20000-02015
Plan Check / Job No.
B20VN07972
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (20'-0"x 24'-0") DETACHED ACCESSORY DWELLING UNIT. WORK PER LA STD WFPP.
Permit Issued
Issued on 8/21/2020
Issuing Office
Current Status
CofO Issued on 1/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2020 APPLICANT
Assigned to Plan Check Engineer 7/30/2020 TROY DEGUZMAN
Corrections Issued 8/1/2020 TROY DEGUZMAN
Quality Review Completed 8/3/2020 CHON CHIO KUO
Building Plans Picked Up 8/5/2020 APPLICANT
Plan Check Approved 8/20/2020 TROY DEGUZMAN
Issued 8/21/2020 APPLICANT
CofO in Progress 12/16/2020 MICHEL ABAJAN
CofO Issued 1/23/2021 MICHAEL SMITH
Permit Finaled 1/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/5/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 8/5/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/11/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/11/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/18/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 9/18/2020 Partial Approval MICHEL ABAJAN
Deputy Reinf. Concrete 9/22/2020 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 9/28/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 10/9/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 10/9/2020 Approved MICHEL ABAJAN
Green Building Rough 10/9/2020 Approved MICHEL ABAJAN
HVAC-Rough 10/9/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 10/9/2020 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 10/9/2020 Approved MICHEL ABAJAN
Insulation 10/14/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/14/2020 Approved MICHEL ABAJAN
Drywall Nailing 10/19/2020 Approved MICHEL ABAJAN
Final 12/1/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 12/1/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/1/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 12/1/2020 Corrections Issued MICHEL ABAJAN
Smoke Detectors 12/1/2020 Approved MICHEL ABAJAN
Final 12/7/2020 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 12/7/2020 Approved MICHEL ABAJAN
Final 12/11/2020 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Final 12/16/2020 Approved MICHEL ABAJAN
Final 12/16/2020 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 12/16/2020 Approved MICHEL ABAJAN
PLUMBING-Final 12/16/2020 Approved MICHEL ABAJAN