437 1/2 W 52ND PL 90037

Certificate Information: 437 1/2 W 52ND PL 90037

Application / Permit
20010-20000-02013
Plan Check / Job No.
B20VN07968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 15' X 28' IRREGULAR SHAPED (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 6/9/2021
Issuing Office
Current Status
CofO Issued on 12/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2020 APPLICANT
Assigned to Plan Check Engineer 8/7/2020 RAPHAEL ROSAS
Corrections Issued 8/11/2020 RAPHAEL ROSAS
Quality Review Completed 8/11/2020 CHON CHIO KUO
Applicant returned to address corrections 4/7/2021 RAPHAEL ROSAS
Applicant returned to address corrections 5/25/2021 RAPHAEL ROSAS
Plan Check Approved 6/9/2021 RAPHAEL ROSAS
Issued 6/9/2021 APPLICANT
Building Plans Picked Up 6/10/2021 APPLICANT
CofO in Progress 12/5/2023 SABAS ALONSO
Permit Finaled 12/7/2023 DEROLD HAUFF
CofO Issued 12/7/2023 DEROLD HAUFF
Permit Finaled 12/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/20/2020 JEANIE LAM
Permit Cleared 8/20/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 8/20/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 2/3/2021 JEANIE LAM
Sewer availability Cleared 2/3/2021 JEANIE LAM
Hydrant and Access approval Cleared 3/25/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/12/2021 Approved SABAS ALONSO
PLUMBING-Rough 9/10/2021 Approved WILLIAM WREN
Excavation/Setback/Form/Re-Bar 9/24/2021 Approved SABAS ALONSO
Footing/Foundation/Slab 9/24/2021 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/10/2021 No Access for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/10/2021 No Access for Inspection SABAS ALONSO
Green Building Rough 12/10/2021 No Access for Inspection SABAS ALONSO
HVAC-Rough 12/10/2021 No Access for Inspection SABAS ALONSO
MERV13>=Rough 12/10/2021 No Access for Inspection SABAS ALONSO
PLUMBING-Rough 12/10/2021 No Access for Inspection SABAS ALONSO
Verify Sprinkler Sign Off 12/10/2021 No Access for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/15/2021 Approved SABAS ALONSO
ELECTRICAL-Rough 12/15/2021 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Partial Inspection SABAS ALONSO
Green Building Rough 12/15/2021 Approved SABAS ALONSO
MERV13>=Rough 12/15/2021 Approved SABAS ALONSO
PLUMBING-Rough 12/15/2021 Approved SABAS ALONSO
Verify Sprinkler Sign Off 12/15/2021 Approved SABAS ALONSO
Insulation 1/6/2022 Not Ready for Inspection SHAVONNE ESPINOZA
Interior/Exterior Lathing 1/6/2022 Corrections Issued SHAVONNE ESPINOZA
HVAC-Rough 1/7/2022 Approved HORACE FULTZ
Insulation 1/7/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 1/7/2022 Partial Approval HORACE FULTZ
Drywall Nailing 1/25/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 1/25/2022 Approved SABAS ALONSO
Drywall Nailing 1/31/2022 Approved SABAS ALONSO
Shower Pan 1/31/2022 Approved SABAS ALONSO
Sewer 3/11/2022 Approved ADAM ESCOTO
Underground Mechanical 3/11/2022 Partial Approval ADAM ESCOTO
Underground Mechanical 4/1/2022 Approved SABAS ALONSO
ELECTRICAL-Final 5/4/2022 Not Ready for Inspection SABAS ALONSO
Final 5/4/2022 Not Ready for Inspection SABAS ALONSO
Gas Test 5/4/2022 Approved SABAS ALONSO
Green Building Final 5/4/2022 Approved SABAS ALONSO
HVAC-Final 5/4/2022 Corrections Issued SABAS ALONSO
MERV13>=Final 5/4/2022 Approved SABAS ALONSO
PLUMBING-Final 5/4/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Not Ready SABAS ALONSO
Service/Power Release 5/4/2022 Not Required SABAS ALONSO
Smoke Detectors 5/4/2022 Approved SABAS ALONSO
ELECTRICAL-Final 5/23/2022 Approved SABAS ALONSO
Final 5/23/2022 Corrections Issued SABAS ALONSO
HVAC-Final 5/23/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved SABAS ALONSO
Final 4/6/2023 Corrections Issued SABAS ALONSO
Final 9/29/2023 Corrections Issued MICHAEL LEWIS
Final 10/25/2023 Corrections Issued RONNIE MINDANAO
Final 11/30/2023 Partial Inspection CRAIG DAVIS
Final 12/4/2023 OK to Issue CofO SABAS ALONSO
Special/Order Compliance 12/4/2023 Partial Inspection DAVID FEILER