7915 N WILBUR AVE 91335

Certificate Information: 7915 N WILBUR AVE 91335

Application / Permit
20010-20000-02000
Plan Check / Job No.
B20VN07947
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW 25'6" X 41'9" DETACHED ACCESSORY LIVING QUARTERS, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER WFPP
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 9/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2020 APPLICANT
Assigned to Plan Check Engineer 7/9/2020 RARES BODEA
Corrections Issued 7/11/2020 RARES BODEA
Quality Review Completed 7/13/2020 STEVEN KIM
Building Plans Picked Up 7/13/2020 APPLICANT
Applicant returned to address corrections 2/22/2021 RARES BODEA
Plan Check Approved 3/1/2021 RARES BODEA
Issued 3/1/2021 APPLICANT
CofO in Progress 9/22/2021 VINCENT HANLEY
Permit Finaled 9/22/2021 JOHN JANSON
CofO Issued 9/22/2021 JOHN JANSON
Permit Finaled 9/22/2021 JOHN JANSON

Permit Application Clearance Information

Tract Map conditions Cleared 7/13/2020 MIGUEL GAMBOA
ZA Case Cleared 7/13/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 7/14/2020 ADRIAN CASTRO
Sewer availability Cleared 7/14/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Low Impact Development Cleared 2/11/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 2/16/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/4/2021 Approved VINCENT HANLEY
PLUMBING-Rough 3/4/2021 Partial Approval VINCENT HANLEY
Sewer 3/4/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval VINCENT HANLEY
Sewer 3/26/2021 Approved VINCENT HANLEY
Underground Mechanical 3/26/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/14/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/14/2021 Approved VINCENT HANLEY
Green Building Rough 4/14/2021 Approved VINCENT HANLEY
HVAC-Rough 4/14/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/14/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/14/2021 Approved VINCENT HANLEY
Drywall Nailing 4/22/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/22/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 5/28/2021 Approved VINCENT HANLEY
Final 5/28/2021 Corrections Issued VINCENT HANLEY
Gas Test 5/28/2021 Approved VINCENT HANLEY
Green Building Final 5/28/2021 Approved VINCENT HANLEY
PLUMBING-Final 5/28/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/28/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/28/2021 Approved VINCENT HANLEY
Smoke Detectors 5/28/2021 Approved VINCENT HANLEY
Final 6/15/2021 Not Ready for Inspection VINCENT HANLEY
HVAC-Final 6/15/2021 Approved VINCENT HANLEY
Final 9/22/2021 OK to Issue CofO VINCENT HANLEY