8214 N MURIETTA AVE 91402
Certificate Information: 8214 N MURIETTA AVE 91402
- Application / Permit
- 20010-20000-01998
- Plan Check / Job No.
- B20VN07943
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 15' X 40' DETACHED 1-STORY ACCESSORY DWELLING UNIT PER WFPP
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 11/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | JENNIFER LEE |
| Corrections Issued | 6/23/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 6/30/2020 | JENNIFER LEE |
| Applicant returned to address corrections | 3/16/2021 | JENNIFER LEE |
| Plan Check Approved | 4/19/2021 | JENNIFER LEE |
| Issued | 4/26/2021 | APPLICANT |
| Building Plans Picked Up | 4/27/2021 | APPLICANT |
| CofO in Progress | 10/10/2024 | GREGG CUMMINGS |
| CofO Issued | 11/2/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/2/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 7/5/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 10/2/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/16/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/15/2021 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Final | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Final | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 9/15/2021 | No Access for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 3/21/2022 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 7/27/2022 | Partial Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 7/27/2022 | Partial Inspection | DAVID MATSON |
| BUILDING-Rough-Frame | 9/7/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 9/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 9/7/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/6/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 10/6/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 10/6/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 11/17/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/20/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 12/20/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/20/2022 | Corrections Issued | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/20/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 1/13/2023 | Partial Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/23/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/31/2023 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 2/13/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/6/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 3/6/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/3/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 4/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 4/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 4/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 4/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/19/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/19/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/19/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/19/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/19/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 10/19/2023 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 10/19/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/15/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 11/15/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/27/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/27/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 11/27/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/5/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 12/5/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 12/5/2023 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 12/5/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/7/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 12/7/2023 | Approved | GREGG CUMMINGS |
| Insulation | 12/12/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 12/15/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | JUAN VALENZUELA |
| Final | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 1/29/2024 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 2/13/2024 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 2/13/2024 | Approved | GREGG CUMMINGS |
| Final | 3/5/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/5/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 3/5/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 3/5/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/9/2024 | Approved | GREGG CUMMINGS |
| Final | 10/9/2024 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 10/9/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 10/9/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/9/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 10/9/2024 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 10/9/2024 | Approved | GREGG CUMMINGS |