9924 W KESWICK ST 91504
Certificate Information: 9924 W KESWICK ST 91504
- Application / Permit
- 20010-20000-01996
- Plan Check / Job No.
- B20VN07937
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 25'0"X35'0" 1-STORY DETACHED ADU PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | MARVEL DELACRUZ |
| Corrections Issued | 7/11/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 7/16/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/16/2020 | APPLICANT |
| Plan Check Approved | 11/23/2020 | MARVEL DELACRUZ |
| Issued | 12/11/2020 | APPLICANT |
| CofO in Progress | 9/6/2022 | DAVID ANDERSON |
| Permit Finaled | 9/7/2022 | MICHAEL SMITH |
| CofO Issued | 9/7/2022 | MICHAEL SMITH |
| Permit Finaled | 9/7/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/4/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/12/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 9/21/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/21/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/20/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/30/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/4/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 11/23/2020 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/2/2021 | Corrections Issued | BEAU COLLINS |
| PLUMBING-Rough | 2/12/2021 | Partial Approval | BEAU COLLINS |
| Footing/Foundation/Slab | 2/17/2021 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 3/3/2021 | Not Ready for Inspection | BEAU COLLINS |
| Green Building Rough | 3/3/2021 | Not Ready for Inspection | BEAU COLLINS |
| MERV13>=Rough | 3/3/2021 | Not Ready for Inspection | BEAU COLLINS |
| Verify Sprinkler Sign Off | 3/3/2021 | Not Ready for Inspection | BEAU COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2021 | Approved | BEAU COLLINS |
| MERV13>=Rough | 3/5/2021 | Not Ready for Inspection | BEAU COLLINS |
| Wood Frame | 3/9/2021 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 4/5/2021 | Partial Approval | BEAU COLLINS |
| Green Building Rough | 4/5/2021 | Approved | BEAU COLLINS |
| MERV13>=Rough | 4/5/2021 | Approved | BEAU COLLINS |
| Verify Sprinkler Sign Off | 4/5/2021 | Approved | BEAU COLLINS |
| Insulation | 4/13/2021 | Corrections Issued | BEAU COLLINS |
| Shower Pan | 4/13/2021 | Approved | BEAU COLLINS |
| Drywall Nailing | 4/14/2021 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 4/19/2021 | Approved | JOHN HAYES |
| Insulation | 4/19/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/19/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 8/30/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Service/Power Release | 11/8/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Final | 12/20/2021 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | MATTHEW NELSON |
| Final | 1/24/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/24/2022 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Final | 1/24/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 1/24/2022 | Approved | MATTHEW NELSON |
| Final | 4/13/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 4/13/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Not Ready | MATTHEW NELSON |
| ELECTRICAL-Final | 7/13/2022 | Approved | DAVID ANDERSON |
| Final | 7/13/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 7/13/2022 | Corrections Issued | DAVID ANDERSON |
| HVAC-Final | 7/13/2022 | Conditional Approval | DAVID ANDERSON |
| PLUMBING-Final | 7/13/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/13/2022 | SGSOV Approved | DAVID ANDERSON |
| Final | 9/2/2022 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 9/2/2022 | Approved | DAVID ANDERSON |