22833 W CALVERT ST 91367
Certificate Information: 22833 W CALVERT ST 91367
- Application / Permit
- 20010-20000-01985
- Plan Check / Job No.
- B20VN07889
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (33'-9"x 43'-0") IRR SHAPE DETACHED ACCESSORY DWELLING UNIT WITH ATT. (21'-4"x 8'-0") OPEN TRELLIS. WORK PER ENGINEER.
- Permit Issued
- Issued on 11/16/2020
- Issuing Office
- Current Status
- CofO Issued on 3/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | TROY DEGUZMAN |
| Corrections Issued | 7/15/2020 | TROY DEGUZMAN |
| Quality Review Completed | 7/15/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 7/22/2020 | APPLICANT |
| Applicant returned to address corrections | 11/6/2020 | TROY DEGUZMAN |
| Plan Check Approved | 11/16/2020 | TROY DEGUZMAN |
| Issued | 11/16/2020 | APPLICANT |
| CofO in Progress | 3/9/2022 | TROY SANDERS |
| Permit Finaled | 3/11/2022 | JOHN JANSON |
| CofO Issued | 3/11/2022 | JOHN JANSON |
| Permit Finaled | 3/11/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/19/2020 | GABRIEL ROBLES |
| ZI | Cleared | 8/26/2020 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 9/18/2020 | KIRK LINKLATER |
| Low Impact Development | Cleared | 9/30/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 10/20/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arsen, Adzhemyan; Lic. No.: C89103 | 1010 RALEIGH ST APT# 107 GLENDALE, CA 91205 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/18/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/11/2021 | Partial Approval | TROY SANDERS |
| Wood Frame | 1/11/2021 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 4/13/2021 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 4/13/2021 | Approved | TROY SANDERS |
| Green Building Rough | 4/13/2021 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 4/13/2021 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 4/13/2021 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 4/13/2021 | Not Ready for Inspection | TROY SANDERS |
| Wood Frame | 4/13/2021 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 4/22/2021 | Approved | TROY SANDERS |
| Green Building Rough | 4/22/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 4/22/2021 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 4/22/2021 | Approved | TROY SANDERS |
| Insulation | 4/26/2021 | Approved | TROY SANDERS |
| Shower Pan | 4/26/2021 | Approved | TROY SANDERS |
| Drywall Nailing | 5/4/2021 | Approved | TROY SANDERS |
| Gas Test | 5/4/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 5/4/2021 | Approved | TROY SANDERS |
| Underground Mechanical | 5/4/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 10/1/2021 | Approved | TROY SANDERS |
| Final | 10/1/2021 | Corrections Issued | TROY SANDERS |
| Green Building Final | 10/1/2021 | Corrections Issued | TROY SANDERS |
| PLUMBING-Final | 10/1/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 10/1/2021 | Approved | TROY SANDERS |
| Smoke Detectors | 10/1/2021 | Approved | TROY SANDERS |
| Green Building Final | 11/3/2021 | Not Ready for Inspection | TROY SANDERS |
| Final | 3/9/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 3/9/2022 | Approved | TROY SANDERS |