11227 W SUNSHINE TER 91604
Certificate Information: 11227 W SUNSHINE TER 91604
- Application / Permit
- 20010-20000-01983
- Plan Check / Job No.
- B20VN07868
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (24'-0"x 21'-0") IRREGULAR SHAPED TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 1/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/9/2020 | TROY DEGUZMAN |
| Corrections Issued | 7/13/2020 | TROY DEGUZMAN |
| Quality Review Completed | 7/13/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 7/13/2020 | APPLICANT |
| Applicant returned to address corrections | 9/8/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 9/24/2020 | TROY DEGUZMAN |
| Plan Check Approved | 10/29/2020 | TROY DEGUZMAN |
| Issued | 11/2/2020 | APPLICANT |
| CofO in Progress | 12/22/2021 | ARAM AVEDISIAN |
| Permit Finaled | 1/20/2022 | MICHAEL SMITH |
| CofO Issued | 1/20/2022 | MICHAEL SMITH |
| Permit Finaled | 1/20/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/15/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 7/15/2020 | LEE GUILBEAUX |
| Street Frontage | Cleared | 7/15/2020 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 7/28/2020 | WALTER RAMIREZ |
| Distance to fire station | Cleared | 8/25/2020 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 8/25/2020 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 9/8/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 9/8/2020 | TROY DEGUZMAN |
| Green Code | Cleared | 9/8/2020 | TROY DEGUZMAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/28/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 10/8/2020 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 10/28/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/2/2020 | ADRIAN CASTRO |
Contact Information
| Architect | Maio,, Miguel J; Lic. No.: C27923 | 13938 ADDISON STREET SHERMAN OAKS, CA 91423 |
| Contractor | Perfitt John; Lic. No.: 1034808-B | 180 SOUTH CITRUS LOS ANGELES, CA 90036 |
| Engineer | Mercado,, Lizandro; Lic. No.: S4331 | 25583 AVENUE STANFORD VALENCIA, CA 91355 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/17/2020 | No Access for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 12/21/2020 | Corrections Issued | ARAM AVEDISIAN |
| Masonry Wall/Backfill | 1/22/2021 | Partial Approval | ARAM AVEDISIAN |
| Reinforced Masonry Frame | 2/4/2021 | Corrections Issued | THOMAS FINNILA |
| Reinforced Masonry Frame | 2/11/2021 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 3/11/2021 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 3/16/2021 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 3/26/2021 | Approved | ARAM AVEDISIAN |
| Wood Frame | 4/28/2021 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/17/2021 | No Access for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 5/17/2021 | No Access for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 5/17/2021 | No Access for Inspection | JOHN HAYES |
| Wood Frame | 5/17/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2021 | No Access for Inspection | MICHAEL TEMPLE |
| Pre-Inspection | 6/7/2021 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/17/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/7/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/30/2021 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 8/9/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 8/9/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 8/12/2021 | Corrections Issued | ARAM AVEDISIAN |
| Special/Order Compliance | 8/12/2021 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 8/19/2021 | Conditional Approval | ARAM AVEDISIAN |
| HVAC-Rough | 8/19/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/19/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 8/26/2021 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/27/2021 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 8/27/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 8/27/2021 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 8/27/2021 | Approved | ARAM AVEDISIAN |
| Shower Pan | 8/30/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/1/2021 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/3/2021 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 9/8/2021 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/20/2021 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/1/2021 | Approved | ARAM AVEDISIAN |
| Final | 11/16/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 11/16/2021 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/16/2021 | Approved | ARAM AVEDISIAN |
| Final | 11/22/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Green Building Final | 11/22/2021 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2021 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 11/22/2021 | Approved | MATT KELLERMAN |
| Final | 12/2/2021 | Corrections Issued | ARAM AVEDISIAN |
| Final | 12/22/2021 | OK to Issue CofO | ARAM AVEDISIAN |