13460 W VENTURA BLVD 91423

Certificate Information: 13460 W VENTURA BLVD 91423

Application / Permit
20010-20000-01967
Plan Check / Job No.
B20VN07802
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
NEW 63'1"X 48'1" 2-STORY COMMERCIAL BUILDING WITH RETAIL USE ON 1ST FLOOR AND OFFICE USE ON 2ND FLOOR. "COMPLY WITH DEPARTMENT ORDER effective date 10/27/2008. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 7/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2020 APPLICANT
Assigned to Plan Check Engineer 7/16/2020 MARVEL DELACRUZ
Corrections Issued 7/23/2020 MARVEL DELACRUZ
Quality Review Completed 8/5/2020 STEVEN KIM
Building Plans Picked Up 8/7/2020 APPLICANT
Disabled Access Plans Picked Up 8/7/2020 APPLICANT
Green Plans Picked Up 8/7/2020 APPLICANT
Applicant returned to address corrections 9/13/2021 MARVEL DELACRUZ
Applicant returned to address corrections 9/29/2021 MARVEL DELACRUZ
Applicant returned to address corrections 11/17/2021 MARVEL DELACRUZ
Plan Check Approved 11/19/2021 MARVEL DELACRUZ
Issued 12/6/2021 APPLICANT
CofO in Progress 6/4/2024 JOHN KITCKO
Permit Finaled 7/16/2024 RICKEY JACKSON
CofO Issued 7/16/2024 RICKEY JACKSON
Permit Finaled 7/16/2024 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 8/20/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 9/8/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 12/29/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Miscellaneous Cleared 2/24/2021 LAUREN PADICK
ZA Case Cleared 2/24/2021 LAUREN PADICK
ZA Case Cleared 2/24/2021 LAUREN PADICK
Trees in Parkway Cleared 3/8/2021 JOHN KIM
Specific Plan Cleared 3/19/2021 BRANDON WILSON
Driveway location Cleared 3/24/2021 BRANDON WILSON
Internal circulation Cleared 3/24/2021 BRANDON WILSON
Highway dedication Cleared 5/12/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 5/24/2021 MATTHEW CRAIG
Bicycle Parking Cleared 7/8/2021 LEE GUILBEAUX
Permit Cleared 7/29/2021 GABRIEL ROBLES
Comm Cor/Mini-Mall Cleared 8/3/2021 LAUREN PADICK
Comm Cor/Mini-Mall Cleared 8/3/2021 LAUREN PADICK
Frnt yard landscape/Water mgmt Cleared 8/3/2021 LAUREN PADICK
Miscellaneous Cleared 8/3/2021 LAUREN PADICK
Specific Plan Cleared 8/3/2021 LAUREN PADICK
ZI Cleared 8/3/2021 LAUREN PADICK
Low Impact Development Cleared 8/9/2021 MITESH PATEL
Green Code Cleared 8/12/2021 AARON COSTA
Roof/Waste drainage to street Cleared 8/12/2021 JOHN LIN
GPI Written Notices Cleared 9/13/2021 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 9/13/2021 MARVEL DELACRUZ
DAS Clearance Cleared 10/21/2021 MARVEL DELACRUZ

Contact Information

Contractor A M C Group Inc; Lic. No.: 749575-B P O BOX 572110      TARZANA, CA 91357
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2022 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/22/2022 Partial Inspection JOHN KITCKO
Piling/Pier/Caisson 3/22/2022 Partial Inspection JOHN KITCKO
Piling/Pier/Caisson 4/4/2022 Conditional Approval ROBERT DAVIS
Deputy Grading 4/5/2022 Conditional Approval JOHN KITCKO
Deputy Grading 4/7/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 4/7/2022 Partial Inspection JOHN KITCKO
Deputy Grading 4/8/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 4/8/2022 Not Ready for Inspection JOHN KITCKO
Piling/Pier/Caisson 4/14/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 4/15/2022 Conditional Approval JOHN KITCKO
Piling/Pier/Caisson 4/15/2022 Partial Inspection JOHN KITCKO
Deputy Grading 4/18/2022 Approved JOHN KITCKO
Deputy Grading 4/19/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/19/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 4/19/2022 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 4/20/2022 Conditional Approval ROBERT DAVIS
Piling/Pier/Caisson 4/20/2022 Not Ready for Inspection ROBERT DAVIS
Deputy Grading 4/21/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/21/2022 Approved JOHN KITCKO
Deputy Grading 4/22/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 4/26/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 4/26/2022 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 4/27/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 4/27/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 4/28/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 4/28/2022 Partial Inspection JOHN KITCKO
Deputy Reinf. Concrete 4/29/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 5/2/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 5/2/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/3/2022 Conditional Approval JOHN KITCKO
Piling/Pier/Caisson 5/3/2022 Partial Approval JOHN KITCKO
Deputy Grading 5/4/2022 Approved ROBERT DAVIS
Deputy Reinf. Concrete 5/4/2022 Conditional Approval ROBERT DAVIS
Piling/Pier/Caisson 5/4/2022 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/5/2022 Conditional Approval JOHN KITCKO
Piling/Pier/Caisson 5/5/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/6/2022 Conditional Approval JOHN KITCKO
Piling/Pier/Caisson 5/6/2022 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/8/2022 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 6/10/2022 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/10/2022 Corrections Issued JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/14/2022 Corrections Issued JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/15/2022 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/16/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/6/2022 Approved JOHN KITCKO
Footing/Foundation/Slab 7/20/2022 Partial Inspection JOHN KITCKO
Wall Anchors 7/21/2022 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Concrete 7/25/2022 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 7/25/2022 Not Ready for Inspection JOHN KITCKO
Structural Steel Frame 7/26/2022 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 7/27/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/28/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 8/5/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 8/8/2022 Approved JOHN KITCKO
Masonry Wall/Backfill 8/8/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 8/9/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 8/10/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/15/2022 Conditional Approval JOHN KITCKO
Deputy Drilled-In Anchors 8/19/2022 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Partial Approval JOHN KITCKO
Structural Steel Frame 8/23/2022 Partial Inspection JOHN KITCKO
Masonry Wall/Backfill 8/24/2022 Not Ready for Inspection JOHN KITCKO
Deputy Reinf. Masonry 8/25/2022 Approved JOHN KITCKO
Masonry Wall/Backfill 8/25/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Masonry 8/26/2022 Conditional Approval JOHN KITCKO
Deputy Wood Construction 9/12/2022 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Partial Approval JOHN KITCKO
Masonry Wall/Backfill 9/14/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 12/21/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 12/22/2022 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 1/10/2023 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Corrections Issued ROBERT DAVIS
Insulation 1/25/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 2/13/2023 Partial Approval JOHN KITCKO
Green Building Rough 3/15/2023 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 3/15/2023 Partial Inspection STEVEN LEVITT
Verify Sprinkler Sign Off 3/15/2023 Approved JOHN KITCKO
Wood Frame 3/15/2023 Not Ready for Inspection JOHN KITCKO
Deputy Drilled-In Anchors 3/17/2023 Conditional Approval JOHN KITCKO
Green Building Rough 3/23/2023 Approved JOHN KITCKO
Wood Frame 3/23/2023 Approved JOHN KITCKO
Insulation 3/29/2023 Partial Approval JOHN KITCKO
Drywall Nailing 3/31/2023 Partial Approval JOHN KITCKO
Insulation 3/31/2023 Approved JOHN KITCKO
Interior/Exterior Lathing 3/31/2023 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 4/11/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 4/11/2023 Partial Approval JOHN KITCKO
Interior/Exterior Lathing 5/9/2023 Partial Inspection JOHN KITCKO
Drywall Nailing 9/21/2023 Approved JOHN KITCKO
Final 9/21/2023 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 9/21/2023 Approved JOHN KITCKO
Green Building Final 9/21/2023 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 9/21/2023 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 9/21/2023 Not Ready for Inspection JOHN KITCKO
Green Building Final 10/2/2023 Not Ready for Inspection JOHN KITCKO
Green Building Final 10/23/2023 Partial Inspection JOHN KITCKO
Final 2/28/2024 Partial Inspection JOHN KITCKO
Green Building Final 2/28/2024 Not Ready for Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 2/28/2024 SGSOV Approved JOHN KITCKO
Smoke Detectors 2/28/2024 Not Ready for Inspection JOHN KITCKO
Final 5/6/2024 Conditional Approval JOHN KITCKO
Green Building Final 5/6/2024 Approved JOHN KITCKO
Smoke Detectors 5/6/2024 Approved JOHN KITCKO
Final 6/4/2024 OK to Issue CofO JOHN KITCKO