13460 W VENTURA BLVD 91423
Certificate Information: 13460 W VENTURA BLVD 91423
- Application / Permit
- 20010-20000-01967
- Plan Check / Job No.
- B20VN07802
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- NEW 63'1"X 48'1" 2-STORY COMMERCIAL BUILDING WITH RETAIL USE ON 1ST FLOOR AND OFFICE USE ON 2ND FLOOR. "COMPLY WITH DEPARTMENT ORDER effective date 10/27/2008. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- CofO Issued on 7/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2020 | MARVEL DELACRUZ |
| Corrections Issued | 7/23/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 8/5/2020 | STEVEN KIM |
| Building Plans Picked Up | 8/7/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 8/7/2020 | APPLICANT |
| Green Plans Picked Up | 8/7/2020 | APPLICANT |
| Applicant returned to address corrections | 9/13/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/29/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 11/17/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 11/19/2021 | MARVEL DELACRUZ |
| Issued | 12/6/2021 | APPLICANT |
| CofO in Progress | 6/4/2024 | JOHN KITCKO |
| Permit Finaled | 7/16/2024 | RICKEY JACKSON |
| CofO Issued | 7/16/2024 | RICKEY JACKSON |
| Permit Finaled | 7/16/2024 | RICKEY JACKSON |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/8/2020 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 12/29/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | JOHN TRIANTAFYLLOS |
| Miscellaneous | Cleared | 2/24/2021 | LAUREN PADICK |
| ZA Case | Cleared | 2/24/2021 | LAUREN PADICK |
| ZA Case | Cleared | 2/24/2021 | LAUREN PADICK |
| Trees in Parkway | Cleared | 3/8/2021 | JOHN KIM |
| Specific Plan | Cleared | 3/19/2021 | BRANDON WILSON |
| Driveway location | Cleared | 3/24/2021 | BRANDON WILSON |
| Internal circulation | Cleared | 3/24/2021 | BRANDON WILSON |
| Highway dedication | Cleared | 5/12/2021 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 5/24/2021 | MATTHEW CRAIG |
| Bicycle Parking | Cleared | 7/8/2021 | LEE GUILBEAUX |
| Permit | Cleared | 7/29/2021 | GABRIEL ROBLES |
| Comm Cor/Mini-Mall | Cleared | 8/3/2021 | LAUREN PADICK |
| Comm Cor/Mini-Mall | Cleared | 8/3/2021 | LAUREN PADICK |
| Frnt yard landscape/Water mgmt | Cleared | 8/3/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 8/3/2021 | LAUREN PADICK |
| Specific Plan | Cleared | 8/3/2021 | LAUREN PADICK |
| ZI | Cleared | 8/3/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 8/9/2021 | MITESH PATEL |
| Green Code | Cleared | 8/12/2021 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 8/12/2021 | JOHN LIN |
| GPI Written Notices | Cleared | 9/13/2021 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 9/13/2021 | MARVEL DELACRUZ |
| DAS Clearance | Cleared | 10/21/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | A M C Group Inc; Lic. No.: 749575-B | P O BOX 572110 TARZANA, CA 91357 |
| Engineer | Gharai,, Armin; Lic. No.: C61464 | 6701 CORIE LN WEST HILLS, CA 91307 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| DEANDRE HOFFMAN, (818) 374-1182 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2022 | Approved | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Partial Inspection | JOHN KITCKO |
| Piling/Pier/Caisson | 3/22/2022 | Partial Inspection | JOHN KITCKO |
| Piling/Pier/Caisson | 4/4/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Grading | 4/5/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Grading | 4/7/2022 | Approved | JOHN KITCKO |
| Piling/Pier/Caisson | 4/7/2022 | Partial Inspection | JOHN KITCKO |
| Deputy Grading | 4/8/2022 | Approved | JOHN KITCKO |
| Piling/Pier/Caisson | 4/8/2022 | Not Ready for Inspection | JOHN KITCKO |
| Piling/Pier/Caisson | 4/14/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/15/2022 | Conditional Approval | JOHN KITCKO |
| Piling/Pier/Caisson | 4/15/2022 | Partial Inspection | JOHN KITCKO |
| Deputy Grading | 4/18/2022 | Approved | JOHN KITCKO |
| Deputy Grading | 4/19/2022 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/19/2022 | Approved | JOHN KITCKO |
| Piling/Pier/Caisson | 4/19/2022 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/20/2022 | Conditional Approval | ROBERT DAVIS |
| Piling/Pier/Caisson | 4/20/2022 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Grading | 4/21/2022 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/21/2022 | Approved | JOHN KITCKO |
| Deputy Grading | 4/22/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/26/2022 | Approved | JOHN KITCKO |
| Piling/Pier/Caisson | 4/26/2022 | Conditional Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 4/27/2022 | Approved | JOHN KITCKO |
| Piling/Pier/Caisson | 4/27/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/28/2022 | Approved | JOHN KITCKO |
| Piling/Pier/Caisson | 4/28/2022 | Partial Inspection | JOHN KITCKO |
| Deputy Reinf. Concrete | 4/29/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 5/2/2022 | Approved | JOHN KITCKO |
| Piling/Pier/Caisson | 5/2/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 5/3/2022 | Conditional Approval | JOHN KITCKO |
| Piling/Pier/Caisson | 5/3/2022 | Partial Approval | JOHN KITCKO |
| Deputy Grading | 5/4/2022 | Approved | ROBERT DAVIS |
| Deputy Reinf. Concrete | 5/4/2022 | Conditional Approval | ROBERT DAVIS |
| Piling/Pier/Caisson | 5/4/2022 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 5/5/2022 | Conditional Approval | JOHN KITCKO |
| Piling/Pier/Caisson | 5/5/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 5/6/2022 | Conditional Approval | JOHN KITCKO |
| Piling/Pier/Caisson | 5/6/2022 | Partial Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 6/8/2022 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Concrete | 6/10/2022 | Conditional Approval | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Corrections Issued | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 6/14/2022 | Corrections Issued | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Not Ready for Inspection | JOHN KITCKO |
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 7/6/2022 | Approved | JOHN KITCKO |
| Footing/Foundation/Slab | 7/20/2022 | Partial Inspection | JOHN KITCKO |
| Wall Anchors | 7/21/2022 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Concrete | 7/25/2022 | Conditional Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 7/25/2022 | Not Ready for Inspection | JOHN KITCKO |
| Structural Steel Frame | 7/26/2022 | Corrections Issued | JOHN KITCKO |
| Footing/Foundation/Slab | 7/27/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 7/28/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 8/5/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 8/8/2022 | Approved | JOHN KITCKO |
| Masonry Wall/Backfill | 8/8/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 8/9/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 8/10/2022 | Approved | JOHN KITCKO |
| Deputy Reinf. Concrete | 8/15/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Drilled-In Anchors | 8/19/2022 | Approved | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | JOHN KITCKO |
| Structural Steel Frame | 8/23/2022 | Partial Inspection | JOHN KITCKO |
| Masonry Wall/Backfill | 8/24/2022 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Reinf. Masonry | 8/25/2022 | Approved | JOHN KITCKO |
| Masonry Wall/Backfill | 8/25/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Masonry | 8/26/2022 | Conditional Approval | JOHN KITCKO |
| Deputy Wood Construction | 9/12/2022 | Conditional Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Partial Approval | JOHN KITCKO |
| Masonry Wall/Backfill | 9/14/2022 | Partial Approval | JOHN KITCKO |
| Footing/Foundation/Slab | 12/21/2022 | Partial Approval | JOHN KITCKO |
| Deputy Reinf. Concrete | 12/22/2022 | Conditional Approval | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2023 | Not Ready for Inspection | JOHN KITCKO |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Corrections Issued | ROBERT DAVIS |
| Insulation | 1/25/2023 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | JOHN KITCKO |
| Green Building Rough | 3/15/2023 | Not Ready for Inspection | JOHN KITCKO |
| Special/Order Compliance | 3/15/2023 | Partial Inspection | STEVEN LEVITT |
| Verify Sprinkler Sign Off | 3/15/2023 | Approved | JOHN KITCKO |
| Wood Frame | 3/15/2023 | Not Ready for Inspection | JOHN KITCKO |
| Deputy Drilled-In Anchors | 3/17/2023 | Conditional Approval | JOHN KITCKO |
| Green Building Rough | 3/23/2023 | Approved | JOHN KITCKO |
| Wood Frame | 3/23/2023 | Approved | JOHN KITCKO |
| Insulation | 3/29/2023 | Partial Approval | JOHN KITCKO |
| Drywall Nailing | 3/31/2023 | Partial Approval | JOHN KITCKO |
| Insulation | 3/31/2023 | Approved | JOHN KITCKO |
| Interior/Exterior Lathing | 3/31/2023 | Not Ready for Inspection | JOHN KITCKO |
| Drywall Nailing | 4/11/2023 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | JOHN KITCKO |
| Interior/Exterior Lathing | 5/9/2023 | Partial Inspection | JOHN KITCKO |
| Drywall Nailing | 9/21/2023 | Approved | JOHN KITCKO |
| Final | 9/21/2023 | Partial Inspection | JOHN KITCKO |
| Footing/Foundation/Slab | 9/21/2023 | Approved | JOHN KITCKO |
| Green Building Final | 9/21/2023 | Not Ready for Inspection | JOHN KITCKO |
| Reinforced Concrete Frame | 9/21/2023 | Approved | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Not Ready | JOHN KITCKO |
| Smoke Detectors | 9/21/2023 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Final | 10/2/2023 | Not Ready for Inspection | JOHN KITCKO |
| Green Building Final | 10/23/2023 | Partial Inspection | JOHN KITCKO |
| Final | 2/28/2024 | Partial Inspection | JOHN KITCKO |
| Green Building Final | 2/28/2024 | Not Ready for Inspection | JOHN KITCKO |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | JOHN KITCKO |
| Smoke Detectors | 2/28/2024 | Not Ready for Inspection | JOHN KITCKO |
| Final | 5/6/2024 | Conditional Approval | JOHN KITCKO |
| Green Building Final | 5/6/2024 | Approved | JOHN KITCKO |
| Smoke Detectors | 5/6/2024 | Approved | JOHN KITCKO |
| Final | 6/4/2024 | OK to Issue CofO | JOHN KITCKO |