5826 N MELVIN AVE 91356
Certificate Information: 5826 N MELVIN AVE 91356
- Application / Permit
- 20010-20000-01948
- Plan Check / Job No.
- B20VN07746
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- PROPOSED (13' X 18') PATIO COVER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Current Status
- CofO Issued on 9/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | RAPHAEL ROSAS |
| Corrections Issued | 7/4/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 7/8/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Applicant returned to address corrections | 10/2/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 10/28/2020 | RAPHAEL ROSAS |
| Issued | 10/29/2020 | APPLICANT |
| CofO in Progress | 9/28/2022 | SEAN HAUPT |
| CofO Issued | 9/30/2022 | MICHAEL SMITH |
| Permit Finaled | 9/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 8/3/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/4/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 9/16/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2021 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 3/9/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 3/9/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2021 | Not Ready for Inspection | STEVEN BACK |
| Pre-Inspection | 4/19/2021 | Partial Inspection | MICHAEL PELHAM |
| Deputy Wood Construction | 4/27/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 4/30/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 4/30/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/14/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 5/20/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Conditional Approval | STEVEN BACK |
| Interior/Exterior Lathing | 6/4/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/10/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 6/10/2021 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 6/10/2021 | Approved | STEVEN BACK |
| Insulation | 6/16/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Insulation | 6/23/2021 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 7/1/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 10/1/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 3/16/2022 | Approved | SEAN HAUPT |
| Final | 3/16/2022 | Corrections Issued | SEAN HAUPT |
| HVAC-Final | 3/16/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 3/16/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 3/16/2022 | Approved | SEAN HAUPT |
| Smoke Detectors | 3/16/2022 | Approved | SEAN HAUPT |
| Final | 9/27/2022 | OK to Issue CofO | SEAN HAUPT |