5807 N BUCKNELL AVE 91607
Certificate Information: 5807 N BUCKNELL AVE 91607
- Application / Permit
- 20010-20000-01930
- Plan Check / Job No.
- B20VN07654
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ACCESSORY DWELLING UNIT PER LAMC 12.22 A 33 (c) & (d)
- Permit Issued
- Issued on 4/1/2021
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | CHON CHIO KUO |
| Corrections Issued | 7/8/2020 | CHON CHIO KUO |
| Quality Review Completed | 7/9/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/13/2020 | APPLICANT |
| Applicant returned to address corrections | 2/24/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/18/2021 | CHON CHIO KUO |
| Plan Check Approved | 3/31/2021 | CHON CHIO KUO |
| Issued | 4/1/2021 | APPLICANT |
| CofO in Progress | 3/4/2024 | JOHN HAYES |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
| CofO Issued | 4/3/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/3/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/21/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 9/17/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/24/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/28/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Executive Design & Construction Inc; Lic. No.: 896934-B | 7515 CALVIN AVENUE RESEDA, CA 91335 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/15/2021 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 1/14/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 6/21/2022 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 6/21/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 6/21/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 6/21/2022 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 6/21/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/21/2022 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 6/21/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/5/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 7/5/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 7/5/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/5/2022 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/5/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/22/2022 | Corrections Issued | JOHN HAYES |
| HVAC-Rough | 7/22/2022 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 7/22/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/22/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/19/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 8/19/2022 | Approved | JOHN HAYES |
| MERV13>=Rough | 8/19/2022 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 8/19/2022 | Approved | JOHN HAYES |
| Wood Frame | 8/19/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 8/26/2022 | Approved | ALAN MORELOS |
| Insulation | 8/26/2022 | Approved | ALAN MORELOS |
| Special/Order Compliance | 8/26/2022 | Corrections Issued | ALAN MORELOS |
| Drywall Nailing | 9/8/2022 | Approved | ALAN MORELOS |
| Insulation | 9/8/2022 | Approved | ALAN MORELOS |
| Shower Pan | 9/8/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/26/2022 | Approved | CALEB MEISTER |
| Special/Order Compliance | 8/30/2023 | Approved | JOHN HAYES |
| Underground Mechanical | 8/30/2023 | Approved | JOHN HAYES |
| Final | 11/8/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/8/2023 | Approved | JOHN HAYES |
| MERV13>=Final | 11/8/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 11/8/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 11/8/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/11/2023 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/11/2023 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 12/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 12/11/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/16/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 1/16/2024 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 1/16/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 1/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/22/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 1/22/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 1/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/26/2024 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 1/26/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 2/9/2024 | Approved | JENNIFER RABUCHIN |
| Final | 2/9/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/9/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/9/2024 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/9/2024 | Approved | JENNIFER RABUCHIN |