519 N CRESCENT HEIGHTS BLVD 90048

Certificate Information: 519 N CRESCENT HEIGHTS BLVD 90048

Application / Permit
20010-20000-01917
Plan Check / Job No.
B20VN07607
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
NEW 33' X 9' 6" DETACHED 2-CAR CARPORT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 1/27/2021
Issuing Office
Current Status
CofO Issued on 10/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2020 APPLICANT
Assigned to Plan Check Engineer 6/11/2020 GURUNATH NESARAJAH
Corrections Issued 6/11/2020 GURUNATH NESARAJAH
Plan Check Approved 11/24/2020 GURUNATH NESARAJAH
Issued 1/27/2021 APPLICANT
CofO in Progress 10/21/2021 CHRIS CHRISTENSEN
Permit Finaled 10/22/2021 DEROLD HAUFF
CofO Issued 10/22/2021 DEROLD HAUFF
Permit Finaled 10/22/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 6/12/2020 OSCAR CASTRO
Roof/Waste drainage to street Cleared 7/15/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/21/2020 ELENA LOPEZ

Contact Information

Contractor Mir Construction Inc; Lic. No.: 930423-B 16656 CHAPLIN AVENUE      ENCINO, CA 91436
Engineer Andrejic,, Milos M; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2021 Partial Approval CHRIS CHRISTENSEN
METHANE-Barrier 2/24/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 2/24/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/10/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/22/2021 Corrections Issued CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 4/1/2021 Corrections Issued CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 4/27/2021 Conditional Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 5/6/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/6/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/28/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Approved CHRIS CHRISTENSEN
Wood Frame 5/28/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 6/2/2021 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 6/3/2021 No Access for Inspection ELMER BLAND
Drywall Nailing 6/8/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/14/2021 Approved CHRIS CHRISTENSEN
Special/Order Compliance 9/1/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/28/2021 Approved CHRIS CHRISTENSEN
Final 9/28/2021 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/28/2021 Approved CHRIS CHRISTENSEN
METHANE-Final 9/28/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 9/28/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 9/28/2021 Conditional Approval CHRIS CHRISTENSEN
Smoke Detectors 9/28/2021 Approved CHRIS CHRISTENSEN