8633 N AMESTOY AVE 91325
Certificate Information: 8633 N AMESTOY AVE 91325
- Application / Permit
- 20010-20000-01895
- Plan Check / Job No.
- B20VN07514
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (32'-8"x 24'-0") DETACHED 2-STORY ACCESSORY DWELLING UNIT WITH ONE CAR ATT. GARAGE PER LAMC 12.22 A.33 (c) and (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 9/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2020 | TROY DEGUZMAN |
| Corrections Issued | 7/8/2020 | TROY DEGUZMAN |
| Quality Review Completed | 7/9/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 7/15/2020 | APPLICANT |
| Applicant returned to address corrections | 1/7/2021 | TROY DEGUZMAN |
| Plan Check Approved | 1/11/2021 | TROY DEGUZMAN |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 9/7/2022 | JAVIER RAMOS JR |
| Permit Finaled | 9/10/2022 | MICHAEL SMITH |
| CofO Issued | 9/10/2022 | MICHAEL SMITH |
| Permit Finaled | 9/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 8/7/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 9/1/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/3/2020 | YVAINNE GALSIM |
| ZA Case | Cleared | 12/7/2020 | LAUREN PADICK |
| Roof/Waste drainage to street | Cleared | 12/16/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 1/7/2021 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/1/2021 | Partial Approval | MARK JOHNSON |
| Sewer | 9/1/2021 | Not Ready for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 9/13/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 9/21/2021 | Partial Approval | MARK JOHNSON |
| Green Building Rough | 9/21/2021 | Not Ready for Inspection | MARK JOHNSON |
| Verify Sprinkler Sign Off | 9/21/2021 | Approved | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Corrections Issued | MARK JOHNSON |
| HVAC-Rough | 12/21/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 12/21/2021 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/9/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/9/2022 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 2/10/2022 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/14/2022 | Conditional Approval | RAUL OLAGI |
| Green Building Rough | 2/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 2/16/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/18/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 2/24/2022 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 2/24/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 2/28/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Drywall Nailing | 3/1/2022 | Approved | MICHAEL TEMPLE |
| Green Building Rough | 3/1/2022 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 3/1/2022 | Partial Approval | MICHAEL TEMPLE |
| Underground Mechanical | 5/11/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/25/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Not Ready | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 8/8/2022 | Approved | JAVIER RAMOS JR |
| Final | 8/8/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 8/8/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 8/8/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 8/8/2022 | Approved | JAVIER RAMOS JR |
| Final | 9/7/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 9/7/2022 | Approved | JAVIER RAMOS JR |