4924 N AVENIDA ORIENTE 91356

Certificate Information: 4924 N AVENIDA ORIENTE 91356

Application / Permit
20010-20000-01884
Plan Check / Job No.
B20VN07438
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
PROPOSED NEW 18'6" X 12'6" DETACHED PATIO COVER W/ L.A. APPROVED DIRECT VENT OUTDOOR FIREPLACE. ALL WORK PER ENGR DESIGNS
Permit Issued
Issued on 8/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2020 APPLICANT
Assigned to Plan Check Engineer 6/17/2020 HAYATO TSUCHIYA
Corrections Issued 6/18/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 7/23/2020 HAYATO TSUCHIYA
Plan Check Approved 7/26/2020 HAYATO TSUCHIYA
Issued 8/25/2020 APPLICANT
CofO in Progress 4/5/2023 VINCENT HANLEY
Permit Finaled 1/3/2024 JOHN JANSON
CofO Issued 1/3/2024 JOHN JANSON
Permit Finaled 1/3/2024 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/10/2020 ADRIAN CASTRO
Tract Map conditions Cleared 7/10/2020 LAUREN PADICK
ZA Case Cleared 7/10/2020 LAUREN PADICK
ZA Case Cleared 7/10/2020 LAUREN PADICK
ZA Case Cleared 7/10/2020 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 7/14/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 7/26/2020 HAYATO TSUCHIYA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/12/2021 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 1/19/2021 Corrections Issued DAVID SANDOVAL
Deputy Reinf. Concrete 1/21/2021 Partial Approval DAVID SANDOVAL
Verify Sprinkler Sign Off 6/21/2021 Not Ready for Inspection RONALD COWAN
Wood Frame 6/21/2021 Partial Approval RONALD COWAN
Final 3/1/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 3/1/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 3/1/2022 Not Ready for Inspection DAVID SANDOVAL
Verify Sprinkler Sign Off 3/1/2022 Approved DAVID SANDOVAL
Wood Frame 3/1/2022 Approved DAVID SANDOVAL
Final 3/4/2022 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 3/4/2022 Not Ready for Inspection DAVID SANDOVAL
Smoke Detectors 3/4/2022 Approved DAVID SANDOVAL
Final 3/28/2023 No Access for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 3/28/2023 No Access for Inspection DAVID SANDOVAL
Final 4/4/2023 OK to Issue CofO VINCENT HANLEY
Footing/Foundation/Slab 4/4/2023 Approved VINCENT HANLEY