13745 W POLK ST 91342
Certificate Information: 13745 W POLK ST 91342
- Application / Permit
- 20010-20000-01864
- Plan Check / Job No.
- B20VN07389
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33'2" X 18'1" TWO STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | RARES BODEA |
| Corrections Issued | 6/27/2020 | RARES BODEA |
| Quality Review Completed | 6/30/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/1/2020 | APPLICANT |
| Applicant returned to address corrections | 10/13/2021 | RARES BODEA |
| Plan Check Approved | 10/26/2021 | RARES BODEA |
| Issued | 11/15/2021 | APPLICANT |
| CofO in Progress | 9/12/2024 | KEVIN BERBERYAN |
| CofO in Progress | 10/24/2024 | ROBERT GOLD |
| CofO in Progress | 10/24/2024 | ROBERT GOLD |
| No Progress | 10/24/2024 | ROBERT GOLD |
| CofO in Progress | 2/18/2025 | KEVIN BERBERYAN |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
| CofO Issued | 2/27/2025 | RUBEN SALAS |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/7/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/8/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 8/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/23/2021 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 9/24/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Perez,, Manuel Armando; Lic. No.: C73786 | 20850 SORRENTO LN PORTER RANCH, CA 91326 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/29/2021 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/4/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 1/4/2022 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/7/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 1/7/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/11/2022 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 1/11/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 1/20/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 2/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 2/28/2022 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 4/15/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 6/15/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/19/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/19/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 10/19/2022 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Wood Construction | 12/16/2022 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/21/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 12/21/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 12/28/2022 | Conditional Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/9/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 1/9/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/9/2023 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 2/16/2023 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/21/2023 | Approved | ARAM AVEDISIAN |
| Gas Test | 5/11/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Gas Test | 6/9/2023 | Approved | DAVID MATSON |
| Final | 9/11/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 9/11/2023 | Not Ready for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 9/11/2023 | SGSOV Not Ready | ROBERT GOLD |
| Service/Power Release | 9/11/2023 | Not Required | ROBERT GOLD |
| Smoke Detectors | 9/11/2023 | Not Ready for Inspection | ROBERT GOLD |
| Final | 10/23/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 10/23/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Not Ready | KEVIN BERBERYAN |
| Smoke Detectors | 10/23/2023 | Conditional Approval | KEVIN BERBERYAN |
| Final | 12/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 12/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/22/2023 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 12/22/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 1/22/2024 | Approved | MICHEL ABAJAN |
| Final | 1/22/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/22/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/22/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/22/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 1/22/2024 | Approved | MICHEL ABAJAN |
| Final | 4/18/2024 | Conditional Approval | KEVIN BERBERYAN |
| Service/Power Release | 4/18/2024 | Approved | KEVIN BERBERYAN |
| Special/Order Compliance | 10/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 2/18/2025 | OK to Issue CofO | KEVIN BERBERYAN |