1128 W 77TH ST 90044

Certificate Information: 1128 W 77TH ST 90044

Application / Permit
20010-20000-01863
Plan Check / Job No.
B20VN07388
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSORY DWELLING UNIT (35'-2"X39'-0") PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/6/2021
Issuing Office
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 MOHAMMAD ESMAILI
Corrections Issued 6/27/2020 MOHAMMAD ESMAILI
Quality Review Completed 7/27/2020 OMID HEDAYAT
Building Plans Picked Up 7/28/2020 APPLICANT
Plan Check Approved 7/16/2021 MOHAMMAD ESMAILI
Issued 10/6/2021 APPLICANT
CofO in Progress 9/26/2023 MICHAEL LEWIS
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/7/2020 ELAINE LEI
Sewer availability Cleared 5/3/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/4/2021 ELAINE LEI
Low Impact Development Cleared 5/21/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/25/2021 ROSA SILVA
Hydrant and Access approval Cleared 6/8/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2022 Approved HORACE FULTZ
PLUMBING-Rough 2/8/2022 Partial Approval AMY COLIN
Special/Order Compliance 2/8/2022 Partial Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/18/2022 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 2/24/2022 Approved LILIANA PORTILLO
Footing/Foundation/Slab 2/24/2022 Approved LILIANA PORTILLO
Pre-Inspection 3/30/2022 Not Ready for Inspection HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 4/13/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 4/20/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 4/20/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 4/28/2022 Approved LILIANA PORTILLO
Sewer 4/28/2022 Approved LILIANA PORTILLO
Underground Mechanical 4/28/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/16/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 5/16/2022 Conditional Approval LILIANA PORTILLO
HVAC-Rough 5/16/2022 Approved LILIANA PORTILLO
Insulation 5/27/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 5/27/2022 Partial Approval HORACE FULTZ
Drywall Nailing 6/21/2022 Approved LILIANA PORTILLO
Shower Pan 6/21/2022 Corrections Issued LILIANA PORTILLO
Shower Pan 7/15/2022 Not Ready for Inspection LILIANA PORTILLO
Underground Mechanical 7/15/2022 Approved LILIANA PORTILLO
Shower Pan 8/3/2022 Approved LILIANA PORTILLO
Pre-Inspection 10/7/2022 Partial Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 10/27/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/27/2022 Corrections Issued LILIANA PORTILLO
Final 10/27/2022 Corrections Issued LILIANA PORTILLO
Green Building Final 10/27/2022 Corrections Issued LILIANA PORTILLO
Green Building Rough 10/27/2022 Approved LILIANA PORTILLO
HVAC-Final 10/27/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 10/27/2022 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 10/27/2022 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 10/27/2022 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 10/27/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 11/15/2022 Not Ready for Inspection LILIANA PORTILLO
Final 11/15/2022 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 11/15/2022 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 11/15/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 11/15/2022 Approved LILIANA PORTILLO
Service/Power Release 11/15/2022 Not Ready for Inspection LILIANA PORTILLO
Final 8/7/2023 Partial Inspection MICHAEL LEWIS
Green Building Final 8/7/2023 Approved MICHAEL LEWIS
Service/Power Release 8/7/2023 Corrections Issued MICHAEL LEWIS
Final 9/14/2023 Conditional Approval MICHAEL LEWIS
Service/Power Release 9/14/2023 Approved MICHAEL LEWIS
Service/Power Release 9/21/2023 Approved MICHAEL LEWIS
Final 9/25/2023 OK to Issue CofO MICHAEL LEWIS