1128 W 77TH ST 90044
Certificate Information: 1128 W 77TH ST 90044
- Application / Permit
- 20010-20000-01863
- Plan Check / Job No.
- B20VN07388
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT (35'-2"X39'-0") PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- CofO Issued on 10/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 6/27/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 7/27/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 7/28/2020 | APPLICANT |
| Plan Check Approved | 7/16/2021 | MOHAMMAD ESMAILI |
| Issued | 10/6/2021 | APPLICANT |
| CofO in Progress | 9/26/2023 | MICHAEL LEWIS |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
| CofO Issued | 10/4/2023 | DEROLD HAUFF |
| Permit Finaled | 10/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/7/2020 | ELAINE LEI |
| Sewer availability | Cleared | 5/3/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2021 | ELAINE LEI |
| Low Impact Development | Cleared | 5/21/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/25/2021 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 6/8/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/28/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 2/8/2022 | Partial Approval | AMY COLIN |
| Special/Order Compliance | 2/8/2022 | Partial Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/18/2022 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 2/24/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/24/2022 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 3/30/2022 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/13/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/20/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 4/20/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/28/2022 | Approved | LILIANA PORTILLO |
| Sewer | 4/28/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 4/28/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/16/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/16/2022 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 5/16/2022 | Approved | LILIANA PORTILLO |
| Insulation | 5/27/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 5/27/2022 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 6/21/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 6/21/2022 | Corrections Issued | LILIANA PORTILLO |
| Shower Pan | 7/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Underground Mechanical | 7/15/2022 | Approved | LILIANA PORTILLO |
| Shower Pan | 8/3/2022 | Approved | LILIANA PORTILLO |
| Pre-Inspection | 10/7/2022 | Partial Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/27/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 10/27/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/27/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 10/27/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 10/27/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 10/27/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 11/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 11/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 11/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 11/15/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 8/7/2023 | Partial Inspection | MICHAEL LEWIS |
| Green Building Final | 8/7/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 8/7/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 9/14/2023 | Conditional Approval | MICHAEL LEWIS |
| Service/Power Release | 9/14/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 9/21/2023 | Approved | MICHAEL LEWIS |
| Final | 9/25/2023 | OK to Issue CofO | MICHAEL LEWIS |