Pre-Inspection
|
10/4/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
Footing/Foundation/Slab
|
12/9/2021
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
Excavation/Setback/Form/Re-Bar
|
12/10/2021
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Deputy Reinf. Concrete
|
12/17/2021
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
Footing/Foundation/Slab
|
12/20/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
Underground Mechanical
|
12/28/2021
|
Approved
|
ALEJANDRO DE ARTOLA
|
Deputy Reinf. Concrete
|
1/11/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
Excavation/Setback/Form/Re-Bar
|
1/11/2022
|
Approved
|
ALEJANDRO DE ARTOLA
|
Deputy Reinf. Concrete
|
1/12/2022
|
Conditional Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
7/29/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Drywall Nailing
|
8/2/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/10/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/12/2022
|
Partial Approval
|
JOSEPH MCGARRY
|
Floor/Roof Diaphrgm/Shear Wall
|
8/23/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
8/25/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Drywall Nailing
|
8/30/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
9/8/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
9/9/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
9/12/2022
|
Partial Approval
|
SCOTT FINNILA
|
Drywall Nailing
|
9/14/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Green Building Rough
|
9/14/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
12/2/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
12/5/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
12/8/2022
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Rough
|
12/19/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
HVAC-Rough
|
12/19/2022
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
HVAC-Rough
|
3/22/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Rough
|
3/22/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
HVAC-Rough
|
4/12/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Rough
|
4/13/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Rough
|
4/24/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Rough
|
4/25/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
ELECTRICAL-Rough
|
5/1/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
PLUMBING-Rough
|
5/1/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/2/2023
|
Corrections Issued
|
ALIZAH MAYAGOITIA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/8/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/10/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Floor/Roof Diaphrgm/Shear Wall
|
5/30/2023
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
Green Building Rough
|
5/30/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Verify Sprinkler Sign Off
|
5/30/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
BUILDING-Rough-Frame
|
6/5/2023
|
Corrections Issued
|
SCOTT FINNILA
|
ELECTRICAL-Rough
|
6/5/2023
|
Approved
|
SCOTT FINNILA
|
Green Building Rough
|
6/5/2023
|
Approved
|
SCOTT FINNILA
|
PLUMBING-Rough
|
6/5/2023
|
Approved
|
SCOTT FINNILA
|
Verify Sprinkler Sign Off
|
6/5/2023
|
Approved
|
SCOTT FINNILA
|
BUILDING-Rough-Frame
|
6/7/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
BUILDING-Rough-Frame
|
6/14/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
BUILDING-Rough-Frame
|
6/21/2023
|
Approved
|
ALEJANDRO DE ARTOLA
|
Insulation
|
6/21/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Interior/Exterior Lathing
|
6/21/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Insulation
|
6/22/2023
|
Corrections Issued
|
ALEJANDRO DE ARTOLA
|
Insulation
|
6/26/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
Drywall Nailing
|
7/5/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
Interior/Exterior Lathing
|
7/5/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
Shower Pan
|
7/5/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
Sewer
|
9/6/2023
|
Approved
|
BRENDAN MORELLI
|
Underground Mechanical
|
9/6/2023
|
Partial Approval
|
BRENDAN MORELLI
|
ELECTRICAL-Rough
|
9/8/2023
|
Approved
|
ALIZAH MAYAGOITIA
|
Underground Mechanical
|
9/8/2023
|
Partial Approval
|
ALIZAH MAYAGOITIA
|
HVAC-Final
|
10/4/2023
|
Corrections Issued
|
BRENDAN MORELLI
|
PLUMBING-Final
|
10/4/2023
|
Conditional Approval
|
BRENDAN MORELLI
|
ELECTRICAL-Final
|
10/6/2023
|
Approved
|
BRENDAN MORELLI
|
Service/Power Release
|
10/6/2023
|
Approved
|
BRENDAN MORELLI
|
Final
|
10/24/2023
|
Corrections Issued
|
BRENDAN MORELLI
|
Green Building Final
|
10/24/2023
|
Approved
|
BRENDAN MORELLI
|
HVAC-Final
|
10/24/2023
|
Approved
|
BRENDAN MORELLI
|
PLUMBING-Final
|
10/24/2023
|
Approved
|
BRENDAN MORELLI
|
SGSOV-Seismic Gas S/O Valve
|
10/24/2023
|
SGSOV Approved
|
BRENDAN MORELLI
|
Smoke Detectors
|
10/24/2023
|
Approved
|
BRENDAN MORELLI
|
Final
|
11/13/2023
|
Corrections Issued
|
SCOTT FINNILA
|
Final
|
12/5/2023
|
OK to Issue CofO
|
BRENDAN MORELLI
|