2235 S COCHRAN AVE 90016
Certificate Information: 2235 S COCHRAN AVE 90016
- Application / Permit
- 20010-20000-01852
- Plan Check / Job No.
- B20VN07366
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 32' X 18'-10" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/27/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 7/14/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 7/16/2020 | APPLICANT |
| Applicant returned to address corrections | 11/30/2020 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 4/21/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 6/25/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 6/25/2021 | APPLICANT |
| CofO in Progress | 4/13/2022 | JOSE AVILA |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/30/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 10/29/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 10/30/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 10/30/2020 | RENZ SORIANO |
| Construction near power lines | Cleared | 11/2/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/2/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 19221 E NORTHAM ST WEST COVINA, CA 91792 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Sewer | 7/15/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 7/15/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Corrections Issued | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 7/29/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 7/30/2021 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/3/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/3/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 9/3/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/8/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/8/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/8/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/17/2021 | Partial Approval | ALFREDO BALANDRA |
| Green Building Rough | 9/17/2021 | Not Ready for Inspection | ALFREDO BALANDRA |
| Shower Pan | 9/17/2021 | Approved | ALFREDO BALANDRA |
| Verify Sprinkler Sign Off | 9/17/2021 | Approved | ALFREDO BALANDRA |
| Interior/Exterior Lathing | 9/22/2021 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 9/23/2021 | Approved | WILLIAM WREN |
| Insulation | 9/23/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 9/29/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 9/29/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Final | 12/17/2021 | Approved | JOSE AVILA |
| Gas Test | 12/17/2021 | Approved | JOSE AVILA |
| HVAC-Final | 12/17/2021 | Approved | JOSE AVILA |
| PLUMBING-Final | 12/17/2021 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | JOSE AVILA |
| Final | 2/1/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 2/1/2022 | Approved | JOSE AVILA |
| Green Building Final | 2/1/2022 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 2/1/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 2/1/2022 | Approved | JOSE AVILA |
| Final | 4/13/2022 | OK to Issue CofO | JOSE AVILA |