10505 N GLENOAKS BLVD 91331

Certificate Information: 10505 N GLENOAKS BLVD 91331

Application / Permit
20010-20000-01831
Plan Check / Job No.
B20VN07353
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
(N) 2-STORY RETAIL BLDG (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 4/6/2023
Issuing Office
Valley
Current Status
Issued on 4/6/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2020 APPLICANT
Disabled Access Plans Picked Up 6/15/2020 APPLICANT
Green Plans Picked Up 6/24/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 NILOOFAR MEHRAIN
Corrections Issued 7/2/2020 NILOOFAR MEHRAIN
Quality Review Completed 7/9/2020 STEVEN KIM
Building Plans Picked Up 7/13/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/9/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/3/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/10/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/16/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/23/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/9/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/24/2023 NILOOFAR MEHRAIN
Plan Check Approved 4/4/2023 NILOOFAR MEHRAIN
Issued 4/6/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/12/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 8/27/2020 MARKOS PEREZ-BRAN
Trees in Parkway Cleared 9/24/2020 JOHN KIM
Hydrant and Access approval Cleared 11/12/2020 MATTHEW CRAIG
Green Code Cleared 12/1/2020 AARON COSTA
Sewer availability Cleared 12/29/2020 MARKOS PEREZ-BRAN
Low Impact Development Cleared 1/19/2021 JORGE MEJIA LEMUS
Clean Up Green Up Cleared 1/28/2021 TERRI OSBORNE
DAS Clearance Cleared 3/11/2021 NILOOFAR MEHRAIN
Highway dedication Cleared 1/27/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 1/28/2022 DAGOVERTO GUERRERO
Permit Cleared 9/9/2022 ABDULLAH SADOZAI
"T" removal Cleared 2/8/2023 NATHAN ROMINE
Miscellaneous Cleared 2/8/2023 NATHAN ROMINE
Miscellaneous Cleared 2/8/2023 NATHAN ROMINE
"Q" conditions Cleared 2/21/2023 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,
Engineer Adamian,, Garen; Lic. No.: C74459 215 N KENWOOD ST #306      GLENDALE, CA 91206

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2023 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 7/19/2023 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 8/23/2023 No Access for Inspection DANNY RODRIGUEZ
Special/Order Compliance 10/3/2023 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/24/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/24/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 11/6/2023 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 11/7/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/13/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 11/14/2023 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/15/2023 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 11/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 11/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 11/17/2023 Corrections Issued DANNY RODRIGUEZ
Reinforced Masonry Frame 11/17/2023 Corrections Issued DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/20/2023 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 11/21/2023 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 11/21/2023 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 11/22/2023 Conditional Approval JEFFREY DURAN
Special/Order Compliance 12/21/2023 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 1/4/2024 Conditional Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/9/2024 Partial Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/17/2024 Corrections Issued DANNY RODRIGUEZ
Footing/Foundation/Slab 1/17/2024 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/19/2024 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 1/19/2024 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 1/24/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 1/25/2024 Partial Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 1/25/2024 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 1/31/2024 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 1/31/2024 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 1/31/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/12/2024 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 2/12/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/13/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/14/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/15/2024 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/15/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/15/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/16/2024 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 2/16/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/21/2024 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 2/22/2024 Approved JOHN KITCKO
Deputy Reinf. Masonry 2/23/2024 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 2/23/2024 Partial Inspection ANDREW DORSO
Reinforced Masonry Frame 2/23/2024 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 2/27/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/28/2024 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 2/28/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/28/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 2/29/2024 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 2/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 2/29/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/1/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/4/2024 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 3/6/2024 Conditional Approval DANNY RODRIGUEZ
Special/Order Compliance 3/7/2024 Partial Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/8/2024 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 3/8/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 3/8/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/12/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/14/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 3/14/2024 No Access for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 3/14/2024 No Access for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/15/2024 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 3/15/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 3/15/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/18/2024 Approved DANNY RODRIGUEZ
Final 3/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 3/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 3/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 3/18/2024 Conditional Approval DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 3/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/19/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 3/22/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 3/22/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/26/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 3/27/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 3/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 3/27/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/2/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/3/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 4/4/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/4/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/5/2024 Conditional Approval GREGORY POMISH
Deputy Reinf. Masonry 4/8/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/9/2024 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/11/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/12/2024 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 4/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/12/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/15/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/17/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/18/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/19/2024 Approved DANNY RODRIGUEZ
Deputy Reinf. Masonry 4/24/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/25/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 6/20/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 6/21/2024 No Access for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 6/24/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/24/2024 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 6/26/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/26/2024 Partial Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 6/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 6/27/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 6/28/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/3/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/9/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 7/10/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/10/2024 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 7/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/12/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/15/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/16/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/18/2024 Approved DANNY RODRIGUEZ
Masonry Wall/Backfill 7/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/18/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/19/2024 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Masonry 7/22/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/23/2024 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/25/2024 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 7/30/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 7/30/2024 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 7/31/2024 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/9/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/12/2024 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/19/2024 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 11/4/2024 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval DANNY RODRIGUEZ
Special/Order Compliance 3/11/2025 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 6/17/2025 Not Ready for Inspection GREGORY POMISH
Reinforced Concrete Frame 6/17/2025 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 6/17/2025 Not Ready for Inspection GREGORY POMISH
Wood Frame 6/20/2025 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/30/2025 Partial Approval JOHN KITCKO
Green Building Rough 6/30/2025 Partial Approval JOHN KITCKO
Reinforced Concrete Frame 6/30/2025 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 6/30/2025 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/2/2025 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 7/8/2025 Partial Approval GREGORY POMISH
Wood Frame 7/8/2025 Partial Approval GREGORY POMISH
Wood Frame 7/11/2025 Partial Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 7/14/2025 Partial Approval GREGORY POMISH
Reinforced Masonry Frame 7/14/2025 Partial Approval GREGORY POMISH
Wood Frame 7/14/2025 Partial Approval GREGORY POMISH
Insulation 7/23/2025 Approved GREGORY POMISH
Footing/Foundation/Slab 7/28/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 8/5/2025 Partial Approval ROBERT DAVIS
Drywall Nailing 8/14/2025 Partial Inspection ANDREW DORSO
Drywall Nailing 8/19/2025 Approved ANDREW DORSO
Reinforced Masonry Frame 8/27/2025 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 9/5/2025 Partial Approval ROBERT DAVIS
Reinforced Masonry Frame 9/5/2025 Partial Approval ROBERT DAVIS
Final 10/8/2025 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 10/8/2025 Partial Inspection GREGORY POMISH
Green Building Final 10/8/2025 Partial Inspection GREGORY POMISH
Green Building Rough 10/8/2025 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 10/8/2025 Partial Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 10/8/2025 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 10/8/2025 Partial Inspection GREGORY POMISH
Final 2/20/2026 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 2/20/2026 Approved JOHN KITCKO
Green Building Final 2/20/2026 Not Ready for Inspection JOHN KITCKO
Green Building Rough 2/20/2026 Approved JOHN KITCKO
Reinforced Concrete Frame 2/20/2026 Partial Inspection JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 2/20/2026 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 2/20/2026 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 2/20/2026 Not Ready for Inspection JOHN KITCKO
Posting Pre-Inspection 7/14/2026 Partial Inspection JOHN KITCKO