13405 N GLADSTONE AVE 91342
Certificate Information: 13405 N GLADSTONE AVE 91342
- Application / Permit
- 20010-20000-01824
- Plan Check / Job No.
- B20VN07308
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 28'2"X24'8" 2-STORY ADU WITH 4'5"X5'0" PORCH
- Permit Issued
- Issued on 1/12/2021
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2020 | MARVEL DELACRUZ |
| Corrections Issued | 7/1/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 7/7/2020 | STEVEN KIM |
| Building Plans Picked Up | 7/9/2020 | APPLICANT |
| Applicant returned to address corrections | 12/7/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 1/12/2021 | MARVEL DELACRUZ |
| Issued | 1/12/2021 | APPLICANT |
| CofO in Progress | 8/5/2022 | ARAM AVEDISIAN |
| Permit Finaled | 8/31/2022 | DANIEL ORRANTE |
| CofO Issued | 8/31/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/31/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/16/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 8/17/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/18/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/23/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 1/12/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John Marshall; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/19/2021 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/21/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/25/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/12/2021 | Conditional Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 3/2/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 3/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 3/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/2/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2021 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 3/16/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 3/16/2021 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/16/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/4/2021 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/4/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 5/4/2021 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 5/7/2021 | Conditional Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 5/10/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/10/2021 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 5/10/2021 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/10/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 5/10/2021 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/24/2021 | Corrections Issued | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 5/24/2021 | Partial Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 5/24/2021 | Partial Inspection | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 5/24/2021 | Partial Approval | MICHAEL TEMPLE |
| PLUMBING-Rough | 5/24/2021 | Partial Inspection | MICHAEL TEMPLE |
| Insulation | 6/1/2021 | Conditional Approval | MISAEL ESPARZA |
| Shower Pan | 6/1/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 6/15/2021 | Approved | MISAEL ESPARZA |
| Green Building Rough | 6/15/2021 | Approved | MISAEL ESPARZA |
| Insulation | 6/15/2021 | Approved | MISAEL ESPARZA |
| Shower Pan | 6/15/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 6/21/2021 | Approved | MISAEL ESPARZA |
| Shower Pan | 6/21/2021 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 8/12/2021 | Partial Approval | MISAEL ESPARZA |
| Gas Test | 8/16/2021 | Partial Approval | MISAEL ESPARZA |
| Grounding or Bonding | 9/28/2021 | No Access for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 9/28/2021 | No Access for Inspection | JOHN HAYES |
| Service/Power Release | 10/7/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 11/9/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/30/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/30/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 11/30/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 11/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 11/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 6/17/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 6/17/2022 | Approved | MATT KELLERMAN |
| MERV13>=Final | 6/17/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2022 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 6/17/2022 | Corrections Issued | MATT KELLERMAN |
| Smoke Detectors | 6/17/2022 | Approved | MATT KELLERMAN |
| Final | 6/24/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 8/5/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 8/5/2022 | Approved | ARAM AVEDISIAN |