13405 N GLADSTONE AVE 91342

Certificate Information: 13405 N GLADSTONE AVE 91342

Application / Permit
20010-20000-01824
Plan Check / Job No.
B20VN07308
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'2"X24'8" 2-STORY ADU WITH 4'5"X5'0" PORCH
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 8/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2020 APPLICANT
Assigned to Plan Check Engineer 6/26/2020 MARVEL DELACRUZ
Corrections Issued 7/1/2020 MARVEL DELACRUZ
Quality Review Completed 7/7/2020 STEVEN KIM
Building Plans Picked Up 7/9/2020 APPLICANT
Applicant returned to address corrections 12/7/2020 MARVEL DELACRUZ
Plan Check Approved 1/12/2021 MARVEL DELACRUZ
Issued 1/12/2021 APPLICANT
CofO in Progress 8/5/2022 ARAM AVEDISIAN
Permit Finaled 8/31/2022 DANIEL ORRANTE
CofO Issued 8/31/2022 DANIEL ORRANTE
Permit Finaled 8/31/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/15/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/16/2020 GABRIEL ROBLES
Sewer availability Cleared 7/16/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 8/17/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/18/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/23/2020 GABRIEL ROBLES
Green Code Cleared 1/12/2021 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John Marshall; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/19/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 1/21/2021 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 1/25/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/12/2021 Conditional Approval BEAU COLLINS
BUILDING-Rough-Frame 3/2/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 3/2/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 3/16/2021 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Rough 3/16/2021 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 3/16/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/4/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 5/4/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 5/4/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 5/4/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 5/4/2021 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 5/7/2021 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 5/10/2021 Approved MISAEL ESPARZA
ELECTRICAL-Rough 5/10/2021 Approved MISAEL ESPARZA
HVAC-Rough 5/10/2021 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/10/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/10/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/24/2021 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 5/24/2021 Partial Inspection MICHAEL TEMPLE
HVAC-Rough 5/24/2021 Partial Inspection MICHAEL TEMPLE
Interior/Exterior Lathing 5/24/2021 Partial Approval MICHAEL TEMPLE
PLUMBING-Rough 5/24/2021 Partial Inspection MICHAEL TEMPLE
Insulation 6/1/2021 Conditional Approval MISAEL ESPARZA
Shower Pan 6/1/2021 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 6/15/2021 Approved MISAEL ESPARZA
Green Building Rough 6/15/2021 Approved MISAEL ESPARZA
Insulation 6/15/2021 Approved MISAEL ESPARZA
Shower Pan 6/15/2021 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 6/21/2021 Approved MISAEL ESPARZA
Shower Pan 6/21/2021 Approved MISAEL ESPARZA
Underground Mechanical 8/12/2021 Partial Approval MISAEL ESPARZA
Gas Test 8/16/2021 Partial Approval MISAEL ESPARZA
Grounding or Bonding 9/28/2021 No Access for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 9/28/2021 No Access for Inspection JOHN HAYES
Service/Power Release 10/7/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 11/9/2021 Not Ready for Inspection JOHN HAYES
Final 11/30/2021 Corrections Issued JOHN HAYES
Green Building Final 11/30/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 11/30/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 11/30/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 11/30/2021 Not Ready for Inspection JOHN HAYES
Final 6/17/2022 Corrections Issued MATT KELLERMAN
Green Building Final 6/17/2022 Approved MATT KELLERMAN
MERV13>=Final 6/17/2022 Approved MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 6/17/2022 SGSOV Approved MATT KELLERMAN
Service/Power Release 6/17/2022 Corrections Issued MATT KELLERMAN
Smoke Detectors 6/17/2022 Approved MATT KELLERMAN
Final 6/24/2022 Not Ready for Inspection ARAM AVEDISIAN
Final 8/5/2022 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 8/5/2022 Approved ARAM AVEDISIAN