1632 S CATALINA ST 90006

Certificate Information: 1632 S CATALINA ST 90006

Application / Permit
20010-20000-01796
Plan Check / Job No.
B20VN07136
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 20'-0" X 30'-0" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 JEROME MAGAT PALMA
Corrections Issued 6/22/2020 JEROME MAGAT PALMA
Quality Review Completed 6/26/2020 STEVEN KIM
Green Plans Picked Up 7/2/2020 APPLICANT
Plan Check Approved 10/27/2021 JEROME MAGAT PALMA
Issued 10/27/2021 APPLICANT
Building Plans Picked Up 10/28/2021 APPLICANT
CofO in Progress 7/29/2022 KATHRYN BUTTERWORTH
CofO Issued 8/3/2022 DEROLD HAUFF
Permit Finaled 8/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/14/2020 ELENA LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/16/2020 ELENA LOPEZ
Sewer availability Cleared 7/16/2020 ELENA LOPEZ
Hydrant and Access approval Cleared 8/20/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/8/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/13/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C91406       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2021 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 11/23/2021 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 11/23/2021 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 11/23/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Sewer 11/23/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 11/23/2021 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 11/30/2021 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 12/1/2021 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 12/6/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 12/17/2021 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/27/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 12/27/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 12/27/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 12/27/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 12/29/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 12/29/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 12/29/2021 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 12/29/2021 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/6/2022 Corrections Issued CRAIG DAVIS
HVAC-Rough 1/6/2022 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 1/6/2022 Approved CRAIG DAVIS
PLUMBING-Rough 1/6/2022 Partial Approval CRAIG DAVIS
Wood Frame 1/6/2022 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 1/10/2022 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 1/10/2022 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 1/11/2022 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 1/11/2022 Approved SCOTT FINNILA
HVAC-Rough 1/11/2022 Approved SCOTT FINNILA
Insulation 1/11/2022 Approved SCOTT FINNILA
PLUMBING-Rough 1/11/2022 Approved SCOTT FINNILA
Wood Frame 1/11/2022 Partial Approval SCOTT FINNILA
Drywall Nailing 1/20/2022 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 1/20/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 1/20/2022 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 1/25/2022 Approved KATHRYN BUTTERWORTH
Drywall Nailing 1/25/2022 Approved KATHRYN BUTTERWORTH
Insulation 1/25/2022 Approved KATHRYN BUTTERWORTH
METHANE-Rough 1/25/2022 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 1/25/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 4/25/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 4/25/2022 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 4/25/2022 Approved KATHRYN BUTTERWORTH
HVAC-Final 4/25/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 4/25/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 4/25/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 4/25/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 5/26/2022 Approved SCOTT FINNILA
Final 5/26/2022 Corrections Issued SCOTT FINNILA
HVAC-Final 5/26/2022 Approved SCOTT FINNILA
PLUMBING-Final 5/26/2022 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Approved SCOTT FINNILA
Service/Power Release 5/26/2022 Approved SCOTT FINNILA
Smoke Detectors 5/26/2022 Approved SCOTT FINNILA
Final 5/27/2022 Corrections Issued SCOTT FINNILA
Final 7/25/2022 Partial Approval KATHRYN BUTTERWORTH
Final 7/26/2022 Corrections Issued KATHRYN BUTTERWORTH
Service/Power Release 7/26/2022 Approved KATHRYN BUTTERWORTH
Final 7/28/2022 OK to Issue CofO KATHRYN BUTTERWORTH