15069 W COBALT ST 91342

Certificate Information: 15069 W COBALT ST 91342

Application / Permit
20010-20000-01788
Plan Check / Job No.
B20VN07104
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 29'-8" x 64'-6" DETACHED ONE-STORY ACCESSORY DWELLING UNIT WITH A TWO-CAR GARAGE.
Permit Issued
Issued on 1/27/2021
Issuing Office
Valley
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 SEAN SHAHMIRI
Corrections Issued 6/21/2020 SEAN SHAHMIRI
Quality Review Completed 7/9/2020 OMID HEDAYAT
Building Plans Picked Up 7/10/2020 APPLICANT
Green Plans Picked Up 7/10/2020 APPLICANT
Applicant returned to address corrections 12/30/2020 SEAN SHAHMIRI
Plan Check Approved 12/30/2020 SEAN SHAHMIRI
Issued 1/27/2021 APPLICANT
Permit Closed-Status Void 12/2/2021 JOHN HAYES
Re-Activate Permit 12/3/2021 JOHN HAYES
CofO in Progress 8/16/2022 ARAM AVEDISIAN
CofO in Progress 8/26/2022 ROBERT GOLD
Permit Finaled 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Issued 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/20/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/3/2020 WALLIE JONG
Sewer availability Cleared 9/3/2020 WALLIE JONG
Hydrant and Access approval Cleared 9/22/2020 MATTHEW CRAIG
ZI Cleared 9/23/2020 PABLO ESTRADA
Low Impact Development Cleared 11/13/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 11/17/2020 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/28/2021 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/19/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 5/19/2021 Conditional Approval MISAEL ESPARZA
PLUMBING-Rough 6/1/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/7/2021 Partial Approval MISAEL ESPARZA
Wood Frame 6/7/2021 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 11/23/2021 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Rough 11/23/2021 Corrections Issued MICHAEL TEMPLE
Green Building Rough 11/23/2021 Not Ready for Inspection MICHAEL TEMPLE
PLUMBING-Rough 11/23/2021 Approved MICHAEL TEMPLE
Underground Mechanical 11/23/2021 Partial Approval MICHAEL TEMPLE
Verify Sprinkler Sign Off 11/23/2021 Approved MICHAEL TEMPLE
ELECTRICAL-Rough 12/2/2021 Partial Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 12/17/2021 Approved JOHN HAYES
Green Building Rough 12/17/2021 Approved JOHN HAYES
Interior/Exterior Lathing 12/17/2021 Partial Approval JOHN HAYES
Rough-Elec/Plmb/HVAC 12/17/2021 Approved JOHN HAYES
Insulation 12/22/2021 Not Ready for Inspection JOHN HAYES
Shower Pan 12/22/2021 Approved JOHN HAYES
Insulation 12/28/2021 Approved JOHN HAYES
Interior/Exterior Lathing 12/28/2021 Approved JOHN HAYES
Drywall Nailing 1/3/2022 Approved JESUS RODRIGUEZ
Final 6/14/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 6/14/2022 Approved ARAM AVEDISIAN
Green Building Final 6/14/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 6/14/2022 Approved ARAM AVEDISIAN
Final 7/27/2022 OK to Issue CofO DEANDRE HOFFMAN
Service/Power Release 7/27/2022 Approved DEANDRE HOFFMAN