7534 W KYLE ST 91042
Certificate Information: 7534 W KYLE ST 91042
- Application / Permit
- 20010-20000-01787
- Plan Check / Job No.
- B20VN07100
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ACCESSORY DWELLING UNIT ( 43'-5"x41'-8") fire sprinkleres NFPA-13D
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/30/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 8/4/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 9/4/2020 | APPLICANT |
| Applicant returned to address corrections | 10/25/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/6/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/10/2022 | ALLEN MANALANSAN |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 5/13/2024 | WILLIAM WREN |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
| CofO Issued | 5/15/2024 | RUBEN SALAS |
| Permit Finaled | 5/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/10/2020 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 1/5/2021 | PATRICK MISCHLICH |
| Construction near power lines | Cleared | 2/10/2021 | RIDWAN HARDY |
| ZI | Cleared | 4/19/2021 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 7/30/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/12/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/17/2021 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 5/6/2022 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/29/2022 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/29/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/8/2022 | Partial Approval | MATTHEW NELSON |
| Grading Pre-Inspection | 11/8/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 11/8/2022 | Partial Approval | MATTHEW NELSON |
| Insulation | 11/14/2022 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Approved | WILLIAM WREN |
| Wood Frame | 12/8/2022 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 12/15/2022 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 1/25/2023 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 1/25/2023 | Not Ready for Inspection | WILLIAM WREN |
| Wood Frame | 1/25/2023 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 2/7/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Rough | 2/7/2023 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 2/7/2023 | Approved | MATTHEW NELSON |
| Wood Frame | 2/7/2023 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/23/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 2/23/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 2/23/2023 | Approved | WILLIAM WREN |
| Insulation | 4/5/2023 | Corrections Issued | WILLIAM WREN |
| Interior/Exterior Lathing | 4/5/2023 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 4/5/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 4/14/2023 | Approved | WILLIAM WREN |
| Insulation | 4/14/2023 | Approved | WILLIAM WREN |
| Shower Pan | 4/25/2023 | Approved | WILLIAM WREN |
| Shower Pan | 5/8/2023 | Approved | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 6/23/2023 | Not Ready for Inspection | WILLIAM WREN |
| Underground Mechanical | 6/23/2023 | Approved | WILLIAM WREN |
| Final | 9/19/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 9/19/2023 | No Access for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 9/19/2023 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 9/19/2023 | Approved | WILLIAM WREN |
| Final | 5/2/2024 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 5/2/2024 | Approved | WILLIAM WREN |
| Service/Power Release | 5/2/2024 | Approved | WILLIAM WREN |