14739 W DRELL ST 91342

Certificate Information: 14739 W DRELL ST 91342

Application / Permit
20010-20000-01783
Plan Check / Job No.
B20VN07089
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19' X 38' 2-STORY ACCESSORY DWELLING UNIT WITH 19' X 10' ATTACHED TRELLIS.
Permit Issued
Issued on 5/5/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2020 APPLICANT
Assigned to Plan Check Engineer 6/19/2020 SERGIO MUNIZ
Corrections Issued 6/22/2020 SERGIO MUNIZ
Quality Review Completed 7/14/2020 OMID HEDAYAT
Green Plans Picked Up 7/16/2020 APPLICANT
Applicant returned to address corrections 3/9/2021 SERGIO MUNIZ
Applicant returned to address corrections 4/13/2021 SERGIO MUNIZ
Plan Check Approved 5/5/2021 SERGIO MUNIZ
Issued 5/5/2021 APPLICANT
Building Plans Picked Up 7/23/2021 APPLICANT
CofO in Progress 7/20/2022 ARAM AVEDISIAN
CofO Issued 7/23/2022 MICHAEL SMITH
Permit Finaled 7/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 6/22/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 6/22/2020 JOHN TRIANTAFYLLOS
ZA Case Cleared 9/21/2020 PABLO ESTRADA
Hydrant and Access approval Cleared 11/10/2020 GILBERT URREA
Low Impact Development Cleared 12/2/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 1/25/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 3/9/2021 JOHN BACON
Hold Cleared 8/19/2021 JASON SHEETS

Contact Information

Architect Mc, Clellan, Robert R; Lic. No.: C3671 38 NORTH LOTUS AVENUE      PASADENA, CA 91107
Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/20/2021 Corrections Issued MISAEL ESPARZA
Underground Mechanical 8/20/2021 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 8/23/2021 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/1/2021 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/3/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 9/3/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/29/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 11/29/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 11/29/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 11/29/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 11/29/2021 Not Ready for Inspection JOHN HAYES
Sewer 11/29/2021 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 11/29/2021 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 12/3/2021 No Access for Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 12/14/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 12/14/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 12/14/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 12/14/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/14/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 12/14/2021 Not Ready for Inspection JOHN HAYES
Underground Mechanical 12/22/2021 Approved JOHN HAYES
ELECTRICAL-Rough 1/3/2022 Approved MICHEL ABAJAN
HVAC-Rough 1/3/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/4/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 1/4/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/4/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 1/4/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/12/2022 Corrections Issued JOHN HAYES
PLUMBING-Rough 1/26/2022 Approved JOHN HAYES
Wood Frame 1/26/2022 Partial Approval JOHN HAYES
Interior/Exterior Lathing 2/4/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 2/10/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 2/10/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/10/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 2/10/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/16/2022 Approved JOHN HAYES
ELECTRICAL-Rough 2/16/2022 Approved JOHN HAYES
Green Building Rough 2/16/2022 Approved JOHN HAYES
Verify Sprinkler Sign Off 2/16/2022 Approved JOHN HAYES
Insulation 2/25/2022 Not Ready for Inspection JOHN HAYES
Shower Pan 2/25/2022 Approved JOHN HAYES
Insulation 3/4/2022 Approved MISAEL ESPARZA
Drywall Nailing 3/11/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 3/11/2022 Approved KRISTEN CAUSEY
Final 7/12/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 7/12/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 7/12/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 7/20/2022 Approved ARAM AVEDISIAN
Final 7/20/2022 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 7/20/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 7/20/2022 Approved ARAM AVEDISIAN
Service/Power Release 7/20/2022 Approved ARAM AVEDISIAN