10267 N TELFAIR AVE 91331
Certificate Information: 10267 N TELFAIR AVE 91331
- Application / Permit
- 20010-20000-01780
- Plan Check / Job No.
- B20VN07086
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 30'-9" x 28'-8" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 12/28/2020
- Issuing Office
- Current Status
- Issued on 12/28/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2020 | SELLA BENYAMIN |
| Corrections Issued | 6/18/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 6/24/2020 | APPLICANT |
| Plan Check Approved | 12/18/2020 | SELLA BENYAMIN |
| Issued | 12/28/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/2/2020 | GABRIEL ROBLES |
| Permit | Cleared | 7/2/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 7/21/2020 | KURT CORRAL |
| Trees in Parkway | Cleared | 7/29/2020 | JOHN KIM |
| Sewer availability | Cleared | 8/12/2020 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 9/9/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/22/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/31/2020 | Partial Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 1/15/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/20/2021 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 1/21/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/21/2021 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/21/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/1/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/1/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/1/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/1/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/1/2021 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 3/1/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/1/2021 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 3/1/2021 | Approved | MICHEL ABAJAN |
| Insulation | 3/4/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/8/2021 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/12/2021 | Approved | MICHEL ABAJAN |
| Final | 4/13/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/13/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 4/13/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 4/13/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/20/2021 | Approved | MICHEL ABAJAN |
| Final | 4/20/2021 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 4/20/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/20/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 4/20/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 4/27/2021 | Partial Inspection | MICHEL ABAJAN |
| Service/Power Release | 4/27/2021 | Not Ready for Inspection | MICHEL ABAJAN |