19116 W STRATHERN ST 91335
Certificate Information: 19116 W STRATHERN ST 91335
- Application / Permit
- 20010-20000-01759
- Plan Check / Job No.
- B20VN07019
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40'-3" X 29'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER WFPP.
- Permit Issued
- Issued on 2/16/2022
- Issuing Office
- Current Status
- CofO Issued on 4/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | ROSENDO MEDINA |
| Corrections Issued | 6/20/2020 | ROSENDO MEDINA |
| Quality Review Completed | 6/24/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 9/28/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 1/27/2022 | ROSENDO MEDINA |
| Plan Check Approved | 2/15/2022 | ROSENDO MEDINA |
| Issued | 2/16/2022 | APPLICANT |
| Building Plans Picked Up | 2/17/2022 | APPLICANT |
| CofO in Progress | 4/4/2023 | JEFFREY BULL |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
| CofO Issued | 4/25/2023 | MICHAEL SMITH |
| Permit Finaled | 4/25/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 8/19/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 9/17/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/26/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 2/14/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/25/2022 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 3/8/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 3/8/2022 | Approved | VINCENT HANLEY |
| Sewer | 4/4/2022 | Approved | VINCENT HANLEY |
| Underground Mechanical | 4/4/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/12/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 10/12/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/12/2022 | Approved | VINCENT HANLEY |
| Insulation | 10/21/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 10/21/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 10/26/2022 | Approved | KRISTEN CAUSEY |
| Shower Pan | 10/26/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/7/2023 | Not Ready for Inspection | JEFFREY BULL |
| Final | 2/7/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 2/7/2023 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 2/7/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 2/7/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 2/7/2023 | Not Ready for Inspection | JEFFREY BULL |
| Smoke Detectors | 2/7/2023 | Approved | JEFFREY BULL |
| Special/Order Compliance | 2/7/2023 | Partial Approval | SEAN WIRCH |
| Verify Sprinkler Sign Off | 2/7/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 4/3/2023 | Approved | JEFFREY BULL |
| Final | 4/3/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 4/3/2023 | Approved | JEFFREY BULL |
| Service/Power Release | 4/3/2023 | Not Required | JEFFREY BULL |