13849 W GILMORE ST 91401
Certificate Information: 13849 W GILMORE ST 91401
- Application / Permit
- 20010-20000-01758
- Plan Check / Job No.
- B20VN07013
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 36'-8" X 20'-5" TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/4/2021
- Issuing Office
- Current Status
- CofO Issued on 11/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/19/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 6/29/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 7/6/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 7/8/2020 | APPLICANT |
| Green Plans Picked Up | 7/8/2020 | APPLICANT |
| Plan Check Approved | 1/22/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 2/4/2021 | APPLICANT |
| CofO in Progress | 10/4/2021 | RICHARD DOCKUS |
| CofO Issued | 11/29/2021 | MICHAEL SMITH |
| Permit Finaled | 11/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/19/2020 | RIDWAN HARDY |
| Address approval | Cleared | 8/26/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 10/2/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/1/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/3/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Star Builders Construction Inc; Lic. No.: 879113-B | 13847 GILMORE STREET VAN NUYS, CA 91401 |
| Engineer | Andrejic,, Milos M; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/22/2021 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 3/22/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/14/2021 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 4/14/2021 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 4/14/2021 | Partial Approval | MATTHEW NELSON |
| Sewer | 4/14/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 4/14/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 4/14/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Wood Construction | 6/4/2021 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/6/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 7/6/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 7/6/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 7/6/2021 | Approved | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 7/6/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 7/13/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 7/13/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 7/13/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 7/13/2021 | Approved | ARTHUR SARGSYAN |
| Gas Test | 9/13/2021 | Approved | RICHARD DOCKUS |
| Service/Power Release | 9/13/2021 | Corrections Issued | RICHARD DOCKUS |
| Sewer | 9/13/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 9/15/2021 | Approved | RICHARD DOCKUS |
| Service/Power Release | 9/15/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| Sewer | 9/15/2021 | Approved | RICHARD DOCKUS |
| Final | 9/28/2021 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 9/28/2021 | Approved | RICHARD DOCKUS |
| HVAC-Final | 9/28/2021 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 9/28/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2021 | SGSOV Approved | RICHARD DOCKUS |
| Service/Power Release | 9/28/2021 | Approved | RICHARD DOCKUS |
| Smoke Detectors | 9/28/2021 | Approved | RICHARD DOCKUS |
| Final | 10/1/2021 | OK to Issue CofO | RICHARD DOCKUS |
| HVAC-Final | 10/1/2021 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 10/19/2021 | Corrections Issued | MICHAEL TEMPLE |