1741 N CORREA WAY 90049

Certificate Information: 1741 N CORREA WAY 90049

Application / Permit
20010-20000-01731
Plan Check / Job No.
B20VN06935
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 12/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2020 APPLICANT
Assigned to Plan Check Engineer 6/18/2020 NILOOFAR MEHRAIN
Corrections Issued 6/25/2020 NILOOFAR MEHRAIN
Quality Review Completed 6/26/2020 STEVEN KIM
Building Plans Picked Up 7/1/2020 APPLICANT
Green Plans Picked Up 7/1/2020 APPLICANT
Applicant returned to address corrections 8/13/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/28/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/3/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/29/2020 NILOOFAR MEHRAIN
Plan Check Approved 10/6/2020 NILOOFAR MEHRAIN
Issued 11/10/2020 APPLICANT
CofO in Progress 12/7/2023 KEVIN SARGSYAN
Permit Finaled 12/18/2023 DANIEL ORRANTE
CofO Issued 12/18/2023 DANIEL ORRANTE
Permit Finaled 12/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/30/2020 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/30/2020 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/30/2020 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/30/2020 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/30/2020 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/31/2020 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 7/31/2020 DENNIS BRAGIN
Sewer availability Cleared 7/31/2020 DENNIS BRAGIN
Low Impact Development Cleared 8/12/2020 ROBIN YAMADA
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Trees in Parkway Cleared 8/25/2020 JOHN KIM
Disturb/Remove Protected Trees Cleared 9/10/2020 NILOOFAR MEHRAIN
GPI Written Notices Cleared 10/6/2020 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 10/6/2020 NILOOFAR MEHRAIN
Green Code Cleared 10/6/2020 NILOOFAR MEHRAIN
Permit Cleared 10/28/2020 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 10/28/2020 MAHELET GEBEYHU

Contact Information

Contractor Southland Building & Remodel Company; Lic. No.: 894311-B 1324 WEST ROSECRANS AVENUE      COMPTON, CA 90222
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/16/2020 Not Ready for Inspection MATT KELLERMAN
Piling/Pier/Caisson 12/21/2020 Approved KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 2/8/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/8/2021 Partial Approval JUAN VALENZUELA
Deputy Shotcrete 2/22/2021 Approved ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 2/22/2021 Conditional Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 2/25/2021 Partial Approval ANDREW NAVE
Deputy Shotcrete 3/5/2021 Approved ROBERT SHELLY
ELECTRICAL-Rough 4/5/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 4/5/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 4/19/2021 Approved JUAN VALENZUELA
Footing/Foundation/Slab 4/19/2021 Approved JUAN VALENZUELA
Deputy Shotcrete 5/10/2021 Corrections Issued ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 8/12/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 1/11/2022 Corrections Issued JUAN VALENZUELA
HVAC-Rough 2/2/2022 Corrections Issued JUAN VALENZUELA
HVAC-Rough 3/9/2022 Partial Inspection JUAN VALENZUELA
PLUMBING-Rough 4/28/2022 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/2/2022 Corrections Issued JUAN VALENZUELA
Green Building Rough 6/2/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 6/2/2022 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 6/2/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 6/10/2022 Approved JUAN VALENZUELA
Green Building Rough 6/10/2022 Approved JUAN VALENZUELA
Drywall Nailing 6/21/2022 Approved JOHN KIDWELL
Shower Pan 7/6/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 7/14/2022 Approved JOHN KIDWELL
Deputy Shotcrete 10/28/2022 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 10/28/2022 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 1/20/2023 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 1/20/2023 Partial Approval KEVIN SARGSYAN
Gas Test 1/20/2023 Approved KEVIN SARGSYAN
Sewer 1/20/2023 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 1/24/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 6/8/2023 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 6/15/2023 Approved EVAN COOPER
PLUMBING-Final 6/15/2023 Approved EVAN COOPER
HVAC-Final 8/31/2023 Corrections Issued KEVIN SARGSYAN
Final 10/24/2023 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 10/24/2023 Approved KEVIN SARGSYAN
Green Building Final 10/24/2023 Approved KEVIN SARGSYAN
HVAC-Final 10/24/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready KEVIN SARGSYAN
Service/Power Release 10/24/2023 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 10/24/2023 Approved KEVIN SARGSYAN
Final 11/27/2023 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 11/27/2023 Approved KEVIN SARGSYAN
Final 12/6/2023 OK to Issue CofO KEVIN SARGSYAN
Service/Power Release 12/6/2023 Approved KEVIN SARGSYAN